Neutral Citation Number: [2023] EWHC 3140 (Admin)
Case No:
CO/1539/2023,
AC-2023-LON-001312;
CO/1577/2023,
AC-2023-LON-001346;
CO/1673/2023,
AC-2023-LON-001419
IN THE HIGH COURT OF JUSTICE
KING'S BENCH DIVISION
ADMINISTRATIVE COURT
Royal Courts of Justice
Strand, London, WC2A 2LL
Date: Wednesday 6
th
December 2023
Before :
THE HONOURABLE MRS JUSTICE THORNTON DBE
- - - - - - - - - - - - - - - - - - - - -
Between :
THE KING (on the application of GABRIEL
CLARKE-HOLLAND)
Claimant
- and -
(1) SECRETARY OF STATE FOR THE HOME
DEPARTMENT
(2) SECRETARY OF STATE FOR LEVELLING
UP, HOUSING AND COMMUNITIES
Defendants
- and -
(1) BRAINTREE DISTRICT COUNCIL
(2) SECRETARY OF STATE FOR DEFENCE
Interested
Parties
And Between :
- - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - -
Mr Goodman KC and Mr McCay appeared on behalf of the Claimant (Mr Clarke-Holland)
Mr Wald KC and Mr Thorold appeared on behalf of the Claimant (West Lindsey District Council)
Mr Beglan and Mr Barber appeared on behalf of the Claimant (Braintree District Council)
Mr Brown KC, Mr Grant and Mr Ronan (instructed by Government Legal Department)
appeared on behalf of the First Defendant (Secretary of State for the Home Department)
Mr Honey KC and Mr Rhimes (instructed by Government Legal Department) appeared on behalf
of the Second Defendant (Secretary of State for Levelling Up, Housing and Communities)
Mr Streeten (instructed by Government Legal Department) appeared on behalf of the Interested
Party (Secretary of State for Defence)
THE KING (on the application of WEST LINDSEY
DISTRICT COUNCIL)
Claimant
- and-
SECRETARY OF STATE FOR THE HOME
DEPARTMENT
Defendant
-and-
(1) SCAMPTON HOLDINGS LIMITED
(2) SECRETARY OF STATE FOR DEFENCE
Interested
Parties
And Between :
THE KING (on the application of BRAINTREE
DISTRICT COUNCIL)
Claimant
- and -
SECRETARY OF STATE FOR THE HOME
DEPARTMENT
- and -
Defendant
SECRETARY STATE FOR DEFENCE
Interested
Party
Hearing dates: 31
st
October 1
st
November 2023
- - - - - - - - - - - - - - - - - - - - -
Approved Judgment
This judgment was handed down remotely at 14:15 on Wednesday 6
th
December 2023 by
circulation to the parties or their representatives by e-mail and by release to the National
Archives.
.............................
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
The Hon. Mrs Justice Thornton :
Introduction
1. The Claimants seek judicial review in relation to the announcement in Parliament on
29 March 2023, by the Minister for Immigration, that the decommissioned Ministry of
Defence sites at Wethersfield and Scampton are to be used to accommodate asylum
seekers.
2. Particular aspects of the decision making under challenge include as follows:
(i) An (undated) statement outlining "the emergency" which is said to thereby
permit lawful reliance on a deemed grant of planning permission under the
Town and Country Planning (General Permitted Development) (England)
Order 2015.
(ii) The direction(s) and/or reliance on the direction(s) issued by the Secretary
of State for Levelling Up, Housing and Communities, pursuant to the
Infrastructure Planning (Environmental Impact Assessment) Regulations
2017 directing that the use of the site in question is not likely to have
significant environmental effects.
(iii) The discharge of the public sector equality duty by the Secretary of State
and the content of an Equalities Impact Assessment.
(iv) The approach taken by the Secretary of State to value for money
considerations.
3. The three claims are brought by Braintree District Council, as the local planning
authority for RAF Wethersfield, West Lindsey District Council, as the local planning
authority for RAF Scampton, and Mr Clarke-Holland, a local resident of Wethersfield.
4. The Secretary of State for the Home Department, who has statutory responsibility for
destitute asylum seekers, is the defendant in all three claims. The Secretary of State for
Levelling Up, Housing and Communities who issued the screening directions is the
second defendant in the claim brought by Mr Clarke-Holland. The Secretary of State
for Defence is an Interested Party in all three claims as the Ministry of Defence owns
both sites.
Factual background
5. The factual background has been outlined in the decisions of the Court of Appeal in
Braintree District Council v Secretary of State for the Home Department [2023] 1 WLR
3087 and by Waksman J in Braintree District Council v Secretary of State for the Home
Department [2023] EWHC 1076 (KB). The following summary focuses on the facts of
particular relevance to the issues which arise in the present case.
The sites
6. Both sites are Crown land, defined as land in which there is a Crown interest, which
includes an interest belonging to a government department (s293 Town and Country
Planning Act 1990).
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
7. RAF Wethersfield covers approximately 828 acres. It contains runways and taxiways,
as well as a number of above ground structures. It is 1.7 miles from the village of
Wethersfield, 2.1 miles from the village of Finchingfield and approximately nine miles
from Braintree and from the nearest A class road. It is accessed via a network of rural
roads, most of which do not have footways.
8. RAF Scampton is located in Lincolnshire. It is 800 acres in size with 280 buildings and
10,000 feet of serviceable runway. The majority of the site is an airfield. RAF
Scampton village is approximately 6 miles from Lincoln and there is a primary school
within walking distance of the site. The site’s history dates back to 1916 and it is
particularly famous for its use during World War II. It is commonly known as the home
of the ‘Dambusters’. In recognition of the site’s historic importance a number of the
structures on site are listed buildings. It was, until recently, an active RAF base and was
decommissioned on 1 April 2023.
The asylum system under strain
9. The Secretary of State for the Home Department has statutory responsibility to provide
accommodation and other support to asylum seekers and their dependants who would
otherwise be destitute. As the Court of Appeal explained in its judgment in Braintree
District Council v Secretary of State for the Home Department [2023] EWCA Civ 727,
the asylum system has, for several reasons, been under increasing strain in recent years.
10. Since the Covid-19 pandemic, the number of asylum seekers requiring accommodation
has reached unprecedented levels. The time taken by the Home Office to process
asylum applications has slowed. The Home Office had for some time been “block
booking” hotel accommodation for use by asylum seekers, a system by which hotel
rooms are booked and paid for, usually at preferential rates, whether or not the rooms
are in fact used. In October and November 2022, a “processing facility” at Manston
became overcrowded. After the overcrowding at Manston, and in light of the increasing
pressure on accommodation, the Home Office started to “spot book” hotels to
accommodate the overflow. Spot bookings can be released without payment if they are
not needed. This approach was controversial with the local authorities in whose areas
the hotels were being booked and, in some cases, they sought injunctions to prevent the
use of hotels for that purpose. Spot booking was intended as a short-term solution, but
the absence of suitable alternative accommodation has led to the continued use of hotels
booked in that way.
The decision making in relation to the use of Wethersfield and Scampton
11. As a result of the strains on the asylum system, in January 2023, the Home Office
approached the Ministry of Defence and other government departments enquiring about
availability of Crown Estate assets which could be made suitable in the short term to
assist with accommodating asylum seekers.
12. A submission to the Minister for Immigration, dated 27 January 2023, sought a decision
to explore the use of RAF Wethersfield and RAF Scampton to accommodate single
adult male asylum seekers. Timing was said to be “immediate”.
13. Initial engagement was undertaken with the two local authorities in question. It revealed
that West Lindsey District Council had plans in relation to the redevelopment of RAF
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
Scampton. In response, Home Office officials initially recommended that the site be
removed from the project. Further investigation into the redevelopment plans led to the
recommendation to Ministers that proposals for the site should continue on the basis
the “Home Office has an urgent operational need to create additional asylum
accommodation, the potential use of RAF Scampton would support this. At present
there are more than 48,000 asylum seekers in hotels and the predicted small boats intake
for 2023 is c.56,000 asylum seekers. The potential use of the site could also provide an
option to mitigate some of the challenges seen at Manston in 2022.”
14. A Ministerial Submission dated 3 March 2023 stated as follows:
“9. To progress rapid development of the Pathfinders and
comply with planning law, we intend to use permitted
development rights for Crown emergency situations (Class Q).
Class Q of Part 19 of Schedule 2 to the Town & Country
Planning (General Permitted Development) (England) Order
2015, will grant us 12 months permission for non-detained use
and related physical works. During this period, we will seek to
ensure that planning permission on a longer-term basis under a
Special Development Order is obtained.
10. To rely on Class Q, we will:
a. prepare a statement outlining the “emergency” which
requires immediate use of the site. We will issue further
advice to you on the Emergency Statement shortly;
b. comply with procedures relating to Environmental Impact
Assessments (EnvIA)
c. comply with procedures relating to Habitats Regulation
Assessments and
d. as soon as is practicable after commencing development,
notify the local planning authority of the development.”
……
39. Given the requirement to expedite delivery for 31 March
2023 there will only be limited engagement with local partners,
and we will not be seeking a local consent decision from
authorities….
40. As part of the engagement on previous sites for asylum
accommodation we have engaged key local partners and
stakeholders including the local MP, leaders and Chief
Executives of the county and district councils and blue light
services. Key themes from this engagement which we expect to
be replicated at the Pathfinder sites include:
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
a. A lack of engagement with the relevant stakeholders / local
community prior to a decision being made to use the sites;
b. anti-social behaviour and Home Office plans to manage this
including keeping local people safe through an increased
police presence in the village;
c. the scale of the site and the impact on local community and
services;
d. remoteness of site how will voluntary and legal services
support the site; and,
e. the relationship between RAF Sites and Rwanda.
…..
Public sector equality duty and vulnerable individuals
….
53. As outlined above there is a significant risk of community
tensions which may impact on the Home Office’s consideration
of limb 3: foster good relations. On the commencement of
engagement with the local community and statutory partners
(including police, fire and health), we will further assess the
impact of the Home Office’s plans. In addition, we will establish
multi-Agency Forums which bring together statutory and other
agencies on a regular basis, both in the implementation stage and
when the site is operational. This will allow the Home Office to
review and update the Equality Impact Assessment. These points
are set out in more detail in the Equality Impact Assessments
(Annex A and Annex B).”
15. A Ministerial Submission dated 23 March 2023 said as follows in relation to duration
of use of Scampton:
Duration of Use
11. A decision on duration of use will have an impact on the
value for money case, HOAI Analysis shows that, based on
current cost estimates the Home Office’s use of RAF Scampton
for 2 years is considered value for money this assumes utilities
are in place. If connection to mains utilities is not possible, then
the proposal would not represent value for money. VfM is more
certain in the short term with high volumes and use of hotel
accommodation, in the longer term there are risks as other factors
impact on demand for accommodation….
12. The Home Office has a statutory duty to accommodate
asylum seekers who would otherwise be destitute and the
number of asylum seekers requiring accommodation has reached
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
record levels. These strategic considerations plus significant
other pressures on the system, such as changing intake patterns,
means that we are of the view that the use of RAF Scampton for
a minimum of 3 years will allow time for other mitigations such
as dispersal to local authorities and case-working transformation
to have a greater effect on the accommodated asylum population.
As above, assuming connection to utilities is possible, HOAI
analysis suggests that the use of the site for longer than 2 years
increases the potential value for money due to longer return on
the initial investment but reduces the certainty as the long-term
position on use of hotels is subject to a number of factors
including the impact of other proposals to reduce demand for
accommodation. Flexibility therefore becomes important with a
longer-term proposal.
(underlining is the original emphasis).
16. As regards financial and accounting implications, it was said that:
25. Finance are engaged with the Programme and assessing
proposals for budgetary impacts and affordability on an ongoing
basis, as well as wider AO implications. Comprehensive AO
advice will be provided imminently and this must be agreed
including by HMT before the sites can be announced/progressed.
A brief summary of early assessments can be found below:
……
c) Value for Money short-term, this proposal may provide
value-for-money under certain conditions, reliant upon the
counterfactual being the use of more costly accommodation.
Longer term forecasts of supply and demand for asylum
accommodation are changeable and could alter the VFM
assessment of this proposal. More detailed costings will be
required to inform this assessment.
17. The same point about the significant risk of community tensions was made as in the
previous submission. The timing was said to be Immediate to inform the
Government’s announcement on Illegal Migration, the decision is urgently required.”
18. An email exchange between officials on 24 March 2023 observed that the Second
Permanent Secretary was content with the value for money analysis, noting the need
for Scampton to have a three year rather than two year economic life to offer positive
value for money. The email went on to state that the Second Permanent Secretary
notes that across the set of decisions there remains a high level of risk, in particular
associated with legal challenge, planning controls, volumes of inflow, hotel costs,
dispersal costs and volumes, overall volumes arrivals and the levels of utilisation across
the different sites”.
19. An earlier email that day recorded that Tricia is satisfied with VfM on Bexhill,
Wethersfield & Scampton on the former two we are saying there is VfM across the 5
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
years planned for the sites...this assumes we are in hotels for that period. If we are not
and/or if our costs are higher than we have estimated, there could be issues on VfM. On
Scampton, our recommendation (with HS) is to use the site for 3 years rather than 2.
VfM for 2 years is currently -£2m, i.e. not VfM (marginal). 3 years is VfM. There are
significant variables here so Tricia should be content with those risks we are not
saying VfM fails. HMT had raised concerns about this but we have provided additional
analysis and talked them through it and we think they are content.”
20. On the same day, the Secretary of State for Levelling Up, Housing and Communities
issued a direction that the proposed use of the site at Wethersfield was not likely to have
significant effects on the environment.
21. An email dated 27 March 2023 from the director of the project for the provision of
asylum accommodation (Mr Banner) indicated that the duration of use of the Scampton
site was still under consideration. Relevant extracts from the email are as follows:
“Further that the HS and Minister Immigration’s positions
regards during of use of Scampton is to consider the site for 2
years. The figures continue to move and latest cost estimates for
the site suggest that the current VfM for 2 years is currently -
£2m i.e. not VfM (marginal), which is an update on the position
in the submission where it states 2 yrs is VfM. Our latest analysis
indicates that 3 years is VfM and is therefore the safest
assessment at present however this could change as we learn
more about the site. The Programme will continue to provide AO
advice as costs iterate.
In our external communication we remain silent on the duration
and suggest we remain silent with MP and partner engagement
as we continue to review our AO position and therefore the
length of time we occupy the site.
In response to handling duration questions I recommend that we
indicate the temporary nature of use i.e. ‘The Home Office will
use RAF Scampton on a temporary basis.’ Or ‘The Home Office
will only use the site for a limited period of time.’”
22. On the same day, Natural England confirmed that there would be no likely significant
effects from the proposed use of the sites on any nearby nature conservation sites.
23. On 28 March 2023, the Secretary of State for Levelling Up, Housing and Communities
issued a direction that the proposed use of the site at Scampton was not likely to have
significant effects on the environment.
24. Still on the same day, the Minister for Immigration was asked to note the Emergency
Statement and agree to the use of Class Q regulations to progress development of both
sites for asylum accommodation. Timing was said to be “Immediate to ensure the
programme can progress following the Home Secretary’s decision to proceed with the
sites, the decision is urgently required.” The point made in the submission of 3 March
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
2023 that Class Q was to be used to progress rapid development of the sites and comply
with planning law” was repeated. The submission did not make reference to a settled
position on the duration of use at the sites.
25. The day after, on 29 March 2023, the Minister for Immigration told the House of
Commons that the sites would be used to accommodate asylum seekers. The Minister
opened his statement by setting out various measures that were being introduced to
tackle illegal migration. These included increased enforcement and removals of people
with no right to remain; Anglo-French co-operation and a partnership with Rwanda to
process claims. The Minister explained that the Home Office was on track to process
the backlog of initial asylum decisions by the end of the year and explained the expected
impact of the Illegal Migration Bill, once adopted. The Statement continues “The
enduring solution to stop the boats is to take the actions outlined in our [Illegal
Migration] Bill but in the meantime, it is right that we act to correct the injustice of the
current situation.”
The decision making documents under challenge
The Emergency Statement
26. The statement identifies the statutory duty on the Secretary of State for the Home
Department to accommodate destitute asylum seekers. It explains the record levels in
the numbers of asylum seekers requiring accommodation. It notes that obtaining
planning permission for new accommodation takes time, and as a consequence, the
Home Office is unable to meet the immediate need for sufficient, adequate
accommodation for asylum seekers”. The statement explains that As of March 2023,
the Home Office is currently accommodating over 48,000 asylum seekers and over
8,000 Afghan refugees in temporary hotel accommodation at a total cost of over £7.2
million per day”. The statement goes on to explain the proposal to use the sites pursuant
to Class Q and explains the nature of the emergency namely the record levels of asylum
seekers which is not thought to have reached its peak; the statutory responsibility on
the Home Secretary; the use of block booked hotels as a short term contingency when
demand for accommodation temporarily exceeds capacity at existing sites in the UK,
which is significantly more expensive and increasingly difficult to source; and the
impacts of Covid on decision making. Reference is also made to the situation at
Manston in October/November 2022 when the Home Office processing centre became
significantly overcrowded which was contributed to by a terrorist attack at another
Home Office site, exacerbated by a significant power outage at Harmondsworth. This
led to spot booking of hotels which was contentious. The development of the sites at
Scampton and Wethersfield will provide additional asylum accommodation.
The screening directions
27. The screening directions for both sites are the same in material respects and conclude
that the proposals for the sites are not likely to have significant effects on the
environment and the development is not therefore EIA Development. In the
accompanying analysis the project is described as the refurbishment of existing
buildings and the construction of new modular buildings to provide residential
accommodation and communal services for non-detained asylum seekers. The project
is said to be for a 12-month period. Pre-fabricated modular units, to provide beds, will
be situated on existing hardstanding and minor groundworks will be required.
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
Renovation of the existing barrack blocks is said to require minimal superficial work.
There will be no construction, engineering works or vegetation clearance and no
demolition. During the decommissioning phase modular units will be removed from
existing hardstanding and transported off site.
28. A number of conclusions reached on the environmental impacts of the project reference
the temporary nature of the project and its 12 month duration. Examples from the
Wethersfield analysis include as follows:
“i) The proposal to accommodate up to a total of up to 1700
people on the Site for a period of 12 months would increase the
demand in the area on water supply and foul water drainage…
Consultation has confirmed…. that there is sufficient capacity
for the provision of water and waste water services for the
Proposed Development.
ii) A total of 204 one way trips each day are estimated over the
temporary 12 month period. This will result in a temporary
impact on the local highway network but the number of vehicle
trips are not considered to be significant in volume.”
The Equality Impact Assessments
29. An Equality Impact Assessment was prepared for both sites and the documents are the
same in material respects. The documents explain that the intention is to use the sites
for asylum accommodation for as long as it remains expedient to do so. The equalities
impact assessment are said to be a living document. Equalities impacts will be kept
under review as proposals develop for the site and as the sites start and continue to be
used. The assessment goes on to explain that the sites are situated in areas that have
not previously been used to house significant numbers of asylum seekers and there may
be impacts on community relations that need to be carefully managed in partnership
with the police, local authorities and others. Reference is made in each assessment to
a nearby primary school which will be discussed as part of local community
engagement. The provision of on-site food, faith, and recreational facilities will
minimise the impact on local communities. The Home Office will work with the
accommodation service provider, police, health and other key stakeholders, including
the community, in order to establish procedures which will manage associated risks in
respect of community relations and to address unease, conflict and a division between
the asylum seekers and the community at large. The Home Office will engage and
consult through scheduled meetings and forums. Once the site is announced, the Home
Office will establish a Multi-Agency Forum, bringing together statutory and other
agencies on a regular basis, both in the implementation stage and when the site is
operational. By working with local police liaison and the local council, the Home Office
will address anti-social behaviour where it may occur through the established support
from the voluntary sector. The site induction pack will include information on the local
environment and ways to avoid anti-social behaviour.
The legal framework
The Secretary of State’s duties in relation to asylum seekers
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
30. Pursuant to sections 95 and 98 of the Immigration and Asylum Act 1999 and regulation
5 of the Asylum Seekers (Reception Conditions) Regulations 2005 (SI 2005/7), if an
asylum seeker or their dependant appears to be destitute or likely to be so while their
application for support under section 95 is being considered, the Secretary of State for
the Home Department must provide them with temporary support which includes
accommodation. The statutory definition of “destitute” includes circumstances in which
a person does not have adequate accommodation or any means of obtaining it.
The need for planning permission and permitted development rights
31. Section 55 of the Town & Country Planning Act 1990 (“TCPA 1990”) provides that
“development” means “the carrying out of building, engineering, mining or other
operations in, on, over or under land, or the making of any material change in the use
of any buildings or other land”. Section 57 of the Act provides that planning permission
is required for “development”. Section 58(1) of the Act provides that: “(1) Planning
permission may be granted (a) by a development order …”.
Permitted Development
32. The Town and Country Planning (General Permitted Development) (England) Order
2015 SI/2015/596 is a development order made pursuant to section 59 TCPA 1990.
Article 3(1) grants planning permission for the classes of development described as
permitted development in Schedule 2. Article 3 provides in relevant parts:
“(1) Subject to the provisions of this Order…planning
permission is hereby granted for the classes of development
described as permitted development in Schedule 2.
(2) Any permission granted by paragraph (1) is subject to any
relevant exception, limitation or condition specified in Schedule
2.
...
(10) Subject to paragraph (12), Schedule 1 development or
Schedule 2 development within the meaning of the Town and
Country Planning (Environmental Impact Assessment)
Regulations 2017 (“the EIA Regulations”) is not permitted by
this Order unless
...
(b) the Secretary of State has made a screening direction under
regulation 5(3) of those Regulations that the development is
not EIA development within the meaning of those
Regulations...
(11) Where
(b) the Secretary of State has directed that development is EIA
development within the meaning of those Regulations that
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
development is treated, for the purposes of paragraph (10), as
development which is not permitted by this Order.”
33. Schedule 2, Part 19 is entitled “Development by the Crown or for national security
purposes”. Class Q provides:
“Q. Permitted development
Development by or on behalf of the Crown on Crown land for
the purposes of
(a) preventing an emergency;
(b) reducing, controlling or mitigating the effects of an
emergency; or
(c) taking other action in connection with an emergency.”
34. Q.1 Conditions:
“Development is permitted by Class Q subject to the following
conditions
(a) the developer must, as soon as practicable after
commencing development, notify the local planning authority
of that development; and
(b) on or before the expiry of the period of 12 months
beginning with the date on which the development began
(i) any use of that land for a purpose of Class Q ceases
and any buildings, plant, machinery, structures and
erections permitted by Class Q is removed; and
(ii) the land is restored to its condition before the
development took place, or to such other state as may
be agreed in writing between the local planning
authority and the developer, unless permission for the
development has been granted by virtue of any
provision of this Schedule or on an application under
Part 3 of the Act.”
Q.2 Interpretation of Class Q:
“(1) For the purposes of Class Q, “emergency” means an event
or situation which threatens serious damage to
(a) human welfare in a place in the United Kingdom;
(b) the environment of a place in the United Kingdom; or
(c) the security of the United Kingdom.
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
(2) For the purposes of sub-paragraph (1)(a), an event or
situation threatens damage to human welfare only if it involves,
causes or may cause
(a) loss of human life;
(b) human illness or injury;
(c) homelessness;
(d) damage to property;
(e) disruption of a supply of money, food, water, energy or
fuel;
(f) disruption of a system of communication;
(g) disruption of facilities for transport; or
(h) disruption of services relating to health.
(3) For the purposes of sub-paragraph (1)(b), an event or
situation threatens damage to the environment only if it involves,
causes or may cause
(a) contamination of land, water or air with biological,
chemical or radioactive matter; or
(b) disruption or destruction of plant life or animal life.
Environmental Impact Assessment
35. Regulation 5(3) of the Town and Country Planning (Environmental Impact
Assessment) Regulations 2017 (SI 2017/571) provides in material part:
“5. – General provisions relating to screening …
(3) A direction of the Secretary of State shall determine for
the purpose of these Regulations whether development is or is
not EIA development.
(4) Where ….. the Secretary of State has to decide under these
Regulations whether Schedule 2 development is EIA
development, the …. Secretary of State must take into account
in making that decision
……
(c) such of the selection criteria set out in Schedule 3 as
are relevant to the development.”
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
36. Schedule 3 is titled “Selection Criteria for Screening”. The criteria include: the
characteristics of the development (including size, design and cumulation with other
existing and/or approved development); the location of the development (including
existing and approved land use, relative abundance of natural resources); as well as the
types and characteristics of the potential impact (including the magnitude and spatial
extent of the impact).
The Public Sector Equality Duty
37. Section 149 of the Equality Act 2010 requires a public authority in the exercise of its
functions, to have due regard to the need to:
“(1)…
(c) foster good relations between persons who share a relevant
protected characteristic and persons who do not share it.
……
(5) Having due regard to the need to foster good relations
between persons who share a relevant protected characteristic
and persons who do not share it involves having due regard, in
particular, to the need to
(a) tackle prejudice, and
(b) promote understanding.”
Grounds of challenge
38. Four grounds of challenge are advanced by the Claimants:
i) Reliance on Class Q permitted development right: All three Claimants challenge
the reliance by the Secretary of State on Class Q permitted development rights
in the General Permitted Development Order. It is said that the Secretary of
State misinterpreted the definition of ‘emergency’ in Part 19, Class Q in the
adoption of her “Emergency Statement”, or alternatively reached an irrational
conclusion under it.
ii) EIA screening directions: Mr Clarke Holland challenges the Screening
Direction issued in relation to Wethersfield as unlawful because it determines
whether there are likely significant effects from the development on the premise
that the development will subsist for a period of only 12 months, which is (a) an
incorrect understanding of the “project” to be assessed, since the project is to
last for longer than 12 months; and/or (b) a failure to consider the cumulative
impacts of the project. Braintree District Council and West Lindsey District
Council challenge the reliance by the Secretary of State for the Home
Department on the screening directions, on the basis that the “project” is in fact
something different and the Secretary of State for the Home Department acted
to frustrate the statutory purpose of the EIA Regulations.
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
iii) Public Sector Equality Duty: Braintree District Council and West Lindsey
District Council contend that the Secretary of State was in breach of her duty
under section 149(1)(c) of the Equality Act to have due regard to the need to
foster good relations between persons who share a relevant protected
characteristic and those that do not. The assessment of community relations in
the Equalities Impact Assessments identifies that the proposal will lead to
asylum seekers being placed in areas of the country not previously used to
accommodating asylum seekers, and that there may be impacts on community
relations. The need for local consultation is identified in the assessment but this
did not, as a matter of fact, take place before the decision to use the site, contrary
to Bridges v Chief Constable of South Wales Police [2020] 1 WLR 5037 at
§175.
iv) Value for money: Braintree District Council contends that in failing to acquire
information available and relied upon within the Home Office about the
necessary operational appraisal period of the Wethersfield Site being (at least)
5 years in order to establish value for money, the Secretary of State for the Home
Department either failed in her duty to acquire information that was necessary
to making a lawful decision; or alternatively left out of account a mandatory
consideration which was bound to have relevance to her decision. As a further
alternative, the Secretary of State proceeded on a mistaken basis, sufficient to
amount to an error of law, that the accounting officer tests were satisfied without
a specific operational period being identified.
Applications before the Court
39. At the hearing, there were two applications before the Court:
i) West Lindsey District Council applied to amend its grounds of claim to refer to
events on the Scampton site postdating the decision under scrutiny which are
said to demonstrate that the Home Office was planning to, or had, undertaken
development at Scampton which had not been screened for its environmental
impacts. The Secretary of State objected to the amendment.
ii) Braintree District Council sought permission to introduce a new ground, namely
the value for money ground set out above. No objection was taken by the
Secretary of State for the Home Department to the introduction of the ground
but it was said to be without merit.
The witness evidence
40. The witness evidence before the Court included as follows:
Evidence adduced by the Claimants
i) An expert report by Dr Darling, an associate professor in human geography at
Durham University produced on behalf of the Claimants. His report addresses
current and previous arrangements for relevant housing provision under sections
95 and 98 of the Immigration and Asylum Act 1999; comparative statistics for
the number of asylum seekers presently and previously; and causes of pressure
on the asylum system and alternatives.
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
ii) A statement from Ms Willman, solicitor and senior consultant at Deighton
Pierce Glynn Solicitors, exhibiting contracts entered into for the provision of
services at the sites.
iii) A statement from Mr Banner, senior civil servant and project director for the
Home Office’s Accommodation Centres Project.
iv) A statement from Mr Burns, senior civil servant and project director for the
Home Office’s Accommodation Centres Project.
v) A statement from Mr Salmon, the head of the Planning Response Unit in the
Department for Levelling Up, Housing and Communities, and who took the
screening decisions.
Discussion
Reliance on Class Q permitted development rights
The decision of Waksman J
41. Waksman J addressed the interpretation of ‘emergency’ for the purposes of Class Q
permitted development rights in Braintree District Council v Secretary of State for the
Home Department & Anor [2023] EWHC 1076 (KB). He treated the question as a
matter of law for the Court to determine. In doing so, he observed that he was not
dealing with a judicial review of the Secretary of State’s decision to adopt the
Emergency Statement (§34). He concluded that ‘emergency’ is exhaustively defined
within paragraph Q2 of Part 19 (§71). A ‘situation’ which threatens serious damage to
human welfare in a place in the United Kingdom contemplates something which may
occur over a period of time and/or which is of a continuing nature (§71). Class Q uses
clear and precise language and whether it applies to any particular case will depend on
the facts of that case (§80). Part Q is concerned only with Crown land. The twelve
month period emphasises the temporary nature of the Class Q right. Originally it was
for six months only (§31).
42. Waksman J rejected the submission by Braintree District Council that he should be
guided by dictionary definitions of “emergency”, which include words like sudden,
unexpected, or unforeseen. He said this would amount to a gloss on the statute where
the statute has provided its own discrete definition (§72). He also rejected the
submission that the obligation on a developer to notify the local planning authority after
commencing the development is an indicator that the right must contemplate some
unforeseen event (§73). Nor did he accept any kind of ranking between Class Q and
section 293A of the Town and Country Planning Act (applications for urgent planning
permission) such that if the event or situation in question truly falls under section 293A,
it cannot also fall within Class Q 76). He rejected the submission that any serious
situation of national significance which government policy seeks to address could, in
theory, allow the government to disregard the planning regime by claiming a Class Q
right (§79).
43. Waksman J applied the law as he considered it to be, to the facts. He concluded that the
unprecedented number of asylum seekers constituted a situation which had emerged
over time (§81). The real prospect of homelessness of asylum seekers in significant
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
numbers absent some further accommodation being found constitutes the threat of
serious damage to human welfare, as defined (§83). He cited the numbers of asylum
seekers as between 120,000 140,000 this year in circumstances when the continued
use of hotels was not sustainable not simply because of cost but because of the issues
with local authorities and the approaching summer months and the award on one
occasion of injunctive relief (§84). The duties of the Secretary of State for the Home
Department mean the reliance on Class Q could not be viewed as a policy question of
how to provide more homes nationwide.
44. The Court of Appeal declined to determine the local authority’s appeal from the
judgment of Waksman J so far as it related to the ambit of Class Q explaining that:
In our judgment it is neither necessary nor desirable to
determine the Class Q point on this appeal. It is not necessary
because our decision on the Jurisdiction Point is determinative
of the appeal. It is not desirable because anything that we say on
this matter would necessarily be obiter dicta and would not bind
the Courts below. Worse, anything we say might put the judge
in another case in which the Class Q point arises at first instance
in a difficult position. At the moment that other judge will have
the benefit of the approach to Class Q set out by Waksman J.
That approach would not bind the other judge, both because
Waksman J’s findings on Class Q were obiter, and because the
other judge would be of co-ordinate jurisdiction. The other judge
would of course be expected to follow Waksman J’s approach
unless that judge considered it to be wrong.” (§64)
45. Turning then to the present case. On behalf of the Secretary of State for the Home
Department it was said that the vast majority of the arguments advanced by the
Claimants in relation to the Class Q issue were addressed in the judgment of Waksman
J. The Court of Appeal has indicated that this Court should only decline to follow
Waksman J’s judgment if convinced it was wrong. Waksman J’s analysis is thorough,
considered, and clearly right.
46. On behalf of the Claimants, it was said that the present claim is a judicial review of the
Secretary of State’s adoption of the “Emergency Statement” with public and planning
law consequences, which were not the subject of Braintree’s application for an
injunction before Waksman J. To the extent there is an overlap with Waksman J’s
decision and the present claim, the judge’s consideration of the Class Q issue was
strictly obiter, as recognised by the Court of Appeal, and the court in fact had no
jurisdiction through those proceedings to determine the issue. The remarks of Waksman
J on the “emergency” point were not informed by a full and frank evidential picture
from the Secretary of State, were wrong in law and ought not to be followed.
The correct approach to interpretation and the role of the Court
47. Waksman J dealt with the question of emergency as a matter of law, observing that he
was not dealing with a judicial review of the Secretary of State’s decision to adopt the
Emergency Statement (§34). It appears from a reading of his judgment that the
Secretary of State had sought to argue before him that the approach to Class Q
encompassed elements of judgement which were matters for the Secretary of State and
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
ought to be afforded deference by the Court (§8). That submission was not however
pursued in the present case. In writing before the hearing, it was said that, on the
particular facts of this case, the Secretary of State was content to proceed on the basis
that the question of emergency is a matter of law, particularly where the vast majority
of arguments raised by the Claimants relate to the interpretation of Class Q rather than
its application. The Secretary of State’s position is reserved on whether the same would
be true of the other categories of “emergency” under Class Q, in particular, national
security. For present purposes, the case advanced was not therefore dependent upon
any argument that there should be any deference to the Secretary of State’s view.
Nonetheless, the submission was made that the claim before this court is a claim for
judicial review, amongst other things, of the Secretary of State’s decision to adopt the
Emergency Statement. To the extent that the Court concludes there are matters of
judgement involved in whether an emergency exists, deference should be given to the
Secretary of State’s administrative judgement in this regard.
48. On behalf of the Claimants, it was said in writing before the hearing that the court
should approach the question of emergency as a matter of law for the court to determine,
at least as it relates to the present case. The question of whether there is, or might be,
an emergency within the meaning of Class Q is a question of law, potentially mixed
with questions of fact. Questions of deference should not be imported into the approach
to Class Q. However, if the court considers that any relevant questions are ones that
can only be challenged by way of Wednesbury review, then, the Claimants also
maintain that the conclusions in the Emergency Statement were not reasonably open to
the Secretary of State and are irrational.
49. The claim before Waksman J concerned an application for an injunction by Braintree
District Council, as local planning authority, pursuant to section 187B TCPA 1990 to
address what it considered to be a breach of planning control. In contrast, the present
claim concerns a judicial review of the decision by the Secretary of State for the Home
Department to adopt the Emergency Statement. The case of R (Mawbey) v Lewisham
London Borough Council [2020] P.T.S.R. 164 concerned a judicial review challenge to
the decision of the local planning authority that electronic communications apparatus
installed on the roof of a house was permitted development under Class A of Part 16 of
the GDPO. The particular issue before the Court was the meaning of the term ‘mast’
used in Class A of Part 16. Lindblom LJ said as follows in relation to the requisite
approach:
“19. … The meaning of the term “mast” in paragraph A.1(2)(c)
is a matter of law. Before a local planning authority can
determine whether a particular structure is a “mast”, it must
adopt the legally correct meaning. In this case, as Lang J. held,
the council did not do that, and thus it erred in law. Its
understanding of the provision was wrong.”
50. Shortly before the hearing, I asked my clerk to email the parties the relevant paragraph
of the decision in R (Mawbey) v Lewisham suggesting that the same approach may be
said to be apt for the present case which also concerns a judicial review of a decision to
rely on permitted development rights. The parties were asked to make any submissions
on the point before the end of the hearing. Nothing was said in response in oral
submissions.
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
51. Accordingly, I propose to start by considering the legally correct meaning of
‘emergency’ on the basis that before the Secretary of State could determine whether the
situation in the present case is an emergency, she must have adopted the legally correct
meaning of the term.
The principles of construction
52. Construing elements of the legislation for planning is not, in essence, a different
exercise from the interpretation of other statutes and statutory instruments. The court’s
essential function is to ascertain the meaning of the words in the legislation having
regard to the purpose of the provisions in question (CAB Housing Ltd v SSLUHC
[2023] EWCA Civ 194 at §22 per Sir Keith Lindblom). The court routinely carries out
the task of interpreting the General Permitted Development Order as an ordinary task
of statutory interpretation, which reflects that the Order is legislation. The ordinary
meaning of the language used is to be ascertained when construing the Order in a broad
or common sense manner. It is to be expected that common words are to be given their
common meaning unless there is something which clearly indicates to the contrary (R
(Mawbey) v Lewisham at §19 and §20).
The interpretation of ‘emergency’
53. Part Q of the General Permitted Development Order opens with paragraph Q, which is
titled “Permitted Development”. It sets out the scope of the right. Permitted
development is “Development by or on behalf of the Crown on Crown land for the
purposes of (a) preventing an emergency; (b) reducing controlling or mitigating the
effects of an emergency; or (c) taking other action in connection with an emergency.
Paragraph Q.1 states that development is permitted by Class Q subject to two
conditions. The first is that the developer must notify the local planning authority of the
development as soon as practicable after commencing it and the second is that any use
must cease on or before the expiry of 12 months unless permission for the development
has been granted. Paragraph Q.2 is headed the interpretation of Class Qand sets
down a definition of ‘emergency’.
54. Two arguments are advanced by the Claimants which, it is said, were either not
advanced before Waksman J or were not articulated in the way now put to the Court.
The first concerns the principle of statutory interpretation that, in the case of a statutory
definition, the defined term may itself colour the meaning of the definition. The
principle is sometimes referred to as ‘the potency of the term defined.’ When the
definition is read as a whole, the ordinary meaning of the word or phrase being defined
forms part of the material which might potentially be used to throw light on the meaning
of the definition. Whether and to what extent it does so depends on the circumstances
and in particular on the terms of the legislation and the nature of the concept referred
to by the word or phrase being defined (see Bennion, Bailey and Norbury on Statutory
Interpretation (8
th
edition) at §18.6 and the Supreme Court decision in R (PACCAR
Inc) v Road Haulage Association [2023] 1 WLR 2594 at §48 (Lord Sales)).
55. Thus, it is said on a proper construction of paragraph Q.2, the definitional paragraph
does not expand the scope of an “emergency” but further defines it. In construing the
individual limbs of the definition, regard must be had to the natural and ordinary
meaning of the word, which, it is apparent from dictionary definitions, includes the
concepts of sudden, unforeseen and unexpected. The absence of a temporal limit to the
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
scope of the right in paragraph Q gives the right a potentially unreasonably broad scope
unless the ordinary meaning of the term emergency is utilised. It is, for example, unclear
at what point it could be said that pressures on the asylum accommodation estate shaded
into an “emergency” on the Secretary of State’s interpretation and development to
mitigate the effects of an emergency could legitimately take place years after the event
or situation giving rise to the alleged emergency.
56. Further, it is said that there is a core meaning to the term “emergency” in the context of
powers afforded to government which imports a restrictive approach. The concept of
“emergency powers” is one that carries a special connotation within constitutional
theory. It is a principle of the rule of law which is manifest in the common law through
the principle of statutory interpretation, that emergency powers, because of their severe
impact and notable departure from ordinary legal norms, are intended to be used
restrictively (Nottingham City Council v Infolines Public Networks Ltd [2010] P.T.S.R.
594 at §9). The effect of Class Q is to disapply the usual rules of planning law,
governing all citizens and it should be interpreted restrictively. Emergency
development under Class Q could plausibly interfere with somebody else’s enjoyment
of their property even if that interference does not amount to a breach of their
proprietary rights. Class Q is not like other permitted development rights in that it is of
such breadth that it can plausibly be used to justify almost any type of development
unless constrained by the core meaning of the term emergency. The Secretary of State’s
conceptualisation of Class Q appears to allow for a “rolling” or “permanent” emergency
which will continue for as long as policies are maintained which engender a population
of asylum seekers and which impose destitution on that population.
57. The second argument which it is said was not articulated before Waksman J in the way
it now is, is that it must be presumed, absent positive evidence to the contrary, that the
Secretary of State for the Home Department will fulfil the statutory duties under
sections 95 and 98 of the Immigration and Asylum Act 1999. There is no evidence
before the Court that it is physically impossible for the duties to be fulfilled absent the
development on the two sites. The expert report of Dr Darling explains the lack of
housing to service the demand faced by those owed the duty is due to a number of
different causes. The increase in demand is only one such factor. The increase in that
demand is, in part, caused by the Secretary of State’s own policy choices inter alia in
allowing a backlog of asylum claimants due to a slowdown in decision-making. The
Secretary of State has a number of available policy levers to reduce the number of
asylum seekers needing accommodation which are not limited to providing more
accommodation. One measure addressed by Dr Darling would be to resume the former
pace and volume at which the Home Office determined asylum applications. There has
already been ample time (whether since the purported emergency began three years
ago, or even in the past three months) for planning applications to have been made
under section 293A TCPA 1990. If the Secretary of State’s interpretation is right, the
approach taken could seemingly be applied to justify “emergency” development to
address the whole gamut of policy problems facing the government. That is entirely
inconsistent with the purpose of the Order and of the removal of Crown immunity
following the coming into force of Part 7 of the Planning and Compulsory Purchase
Act 2004.
58. Other arguments advanced by the Claimants repeat those advanced before Waksman J.
The condition in Q.1 that a developer need only notify the local planning authority of
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
the development as soon as practicable after commencing development indicates that
the event or situation must be unexpected or unforeseen. Finally, the Court’s attention
was drawn to the explanatory notes to the Civil Contingencies Act 2004 which contains
materially similar wording. The examples given of emergencies encompass a sudden,
unexpected, unforeseen event or situation such as a terrorist attack, disruption of fuel
supplies, contamination of land with a chemical matter and an epidemic.
59. Whilst the Claimants’ submissions were cogently expressed, they are, in my view,
defeated by the ordinary meaning of the words used in Part Q. Paragraph Q.2 is headed
“Interpretation of Class Q”. Q.2(1) starts by saying that for the purposes of Class Q
‘emergency’ means. The underlined words indicate the definition that then follows is
intended to be comprehensive, so far as it relates to the application of Class Q. If so,
the term must therefore be understood in its stipulated sense and the Court must take
care not to apply a judicial paraphrase or other gloss on a statutory definition.
60. ‘Emergency’ is said to mean ‘an event or situation’ which ‘threatens serious damage’
to human welfare, the environment or national security. I agree with Waksman J that
‘situation’ contemplates something which may have occurred over a period of time and
which is of a continuing nature. In this regard it may be said that there is an inherent
tension between the reference to ‘situation’ in the definition and the interpretation
proposed by the Claimants which requires the emergency to be sudden, unexpected or
unforeseen. The reference to ‘threatens serious damage’ sets the threshold for an event
or situation to become an emergency for the purposes of Class Q. The threat of serious
damage must relate to one (or more) of three specified categories of harm (human
welfare in a place in the UK, the environment of a place in the UK and the security of
the UK). Serious damage to human welfare is defined by a list in Q .2 (2) which includes
homelessness. The reference to “only if” in the paragraph indicates the list is to be
treated as exhaustive. The same reference to “only if” appears in sub paragraph 3 in
relation to the environment. There is no qualification in relation to serious damage to
the security of the United Kingdom.
61. Turning to the principle of the ‘potency of the term defined’, the Supreme Court in
PACCAR expressed the view that no significant potency can be attached to the term so
as to colour or qualify the meaning of the definition in the absence of general consensus
as to the limits of the term, as here (§49). In any event, the threat of serious damage to
human welfare, the environment or national security accords, in my view, with an
ordinary understanding of the term ‘emergency’. Some of these emergencies could be
sudden, unexpected or unforeseen, but others that are not will still satisfy the threshold
test for the applicability of Class Q if they give rise to the threat of serious damage. I
accept that there is no temporal limit on the scope of the right in paragraph Q. There
are however other limitations to its scope. In addition to the requirement for a threat of
serious damage the development must be on Crown land. It must be development by,
or on behalf of, the Crown. The development is time limited. On or before the expiry
of 12 months the permission ceases and the use/development must be reversed unless
planning permission has been granted (the time limit used to be 6 months but was
extended during Covid).
62. The condition in paragraph Q1 that the developer need only notify the local planning
authority after the development has commenced cannot alter the scope of the right. The
grant of planning permission derives from article 3(1) and the provisions for “permitted
development” in that class not through the specific provisions for “conditions” in a
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
particular class. To be “permitted development” in the first place, the development in
question has to come fully within the relevant description of the “permitted
development” provided for within each class. If it does not, the provisions for
“conditions” applicable specifically and only to “permitted development” as thus
defined could not relate to it. In other words, the conditions imposed on a class of right
cannot have the effect of enlarging the class (Keenan v Woking BC [2018] P.T.S.R.
697 at §33).
63. The decision in Nottingham City Council v Infolines relied on by the Claimants may
be distinguished legally and factually from the present case. It concerned the
interpretation of emergency works’ in an Act of Parliament (The New Roads and Street
Works Act 1991) and the disposal of property belonging to the defendant in the claim.
In any event, however, the scope of emergency in Class Q is restricted. It is restricted
by the requirement for a threat of serious damage in relation to three specified categories
of harm. As for section 293A of the Town & Country Planning Act, there is no
definition in the section as to when it is necessary to carry out development ‘as a matter
of urgency’, which might assist the Claimants in their submission that there ought to be
a ranking as between section 293A and Class Q. Moreover, there is an obvious
distinction with Class Q which only permits development for up to a year. The concept
of ‘ranking’ the applicability of the two provisions suggested by the Claimants is not
therefore apt.
The interpretation of emergency in the Emergency Statement
64. Accordingly, on the interpretation arrived at above, for the Secretary of State to lawfully
rely on the Class Q permitted development right, she must have been able to
demonstrate the existence of an event or situation which threatens serious damage to
human welfare in the UK by virtue of homelessness, which in the present case, relates
to asylum seekers.
65. The Emergency Statement defines the emergency at paragraph 19:
“It is considered that an emergency exists falling within the
definition above since there currently exists in the United
Kingdom a situation which threatens serious damage to human
welfare because there was and remains an immediate need to
provide accommodation for destitute asylum seekers which if
not met would result in homelessness. Whilst a proportion of this
need is currently being met through the use of hotels, this was
(and still is) only intended as a short-term or stop-gap solution
pending provision of more suitable alternatives.
The proposed development would therefore be undertaken:
i) For the purposes of preventing an emergency;
ii) for the purposes of reducing and mitigate the effects of that
emergency; and/or
iii) as “other action” taken in connection with that
emergency.”
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
66. On the construction of emergency the Court has arrived at above, the Secretary of State
used the legally correct construction of emergency in the Emergency Statement.
Application to the facts of the present case
67. Applying the approach of the Court of Appeal in R (Mawbey) v Lewisham, I incline to
the view that the question of whether there is a threat of serious damage by way of
homelessness of asylum seekers requires the application of judgement, which ought,
primarily, to be a matter for the Secretary of State for the Home Department. The Home
Office has statutory responsibility for accommodating destitute asylum seekers and
consequential institutional knowledge and experience in this regard. The exercise of
judgement is subject to review on the usual public law principles.
68. For present purposes, however, it is unnecessary to form a concluded view on the issue
because I am satisfied that the outcome is the same whether the Court applies the law
to the facts itself or reviews the judgement of the Secretary of State in this regard. On
either case the Secretary of State’s reliance on Class Q was, in my view, lawful.
69. The development proposed is development by or on behalf of the Crown, on Crown
Land. It is not disputed that the numbers of asylum seekers are at record levels or that
the Secretary of State has a legal duty to accommodate them. In October/November
2020 a particular crisis point was reached when the processing facility at Manston
became dangerously overcrowded. There can be no serious dispute that ‘spot booking’
or ‘block booking’ hotels is not suitable accommodation or a sustainable longer term
solution. This is due not only to the cost or to the obvious point that hotels are
ordinarily intended for very different purposes. It is also due to the hostile reaction of
local authorities to the practice which resulted in a spate of litigation (Great Yarmouth
v Al-Abdin [2022] EWHC 3476). The numbers of asylum seekers involved are
significant. The Emergency Statement explains that the total number of asylum seekers
receiving support on 31 December 2020 was 110,171 which reflects a 72% increase on
the numbers in December 2020. As of March 2023, the Home Office was
accommodating over 48,000 asylum seekers and over 8000 Afghan refugees in
temporary hotel accommodation. This is a “situation” which “may cause” (Q.2(2)) the
homelessness (Q.2(2)(c)) of large numbers of asylum seekers (which could in turn lead
to “human illness or injury” (2(2)(b)). Given the number of asylum seekers concerned,
and the vulnerability of that cohort, the scale of damage is potentially significant, i.e.
the situation “threatens serious damage” to human welfare (Q.2(1)(a)). This serious
damage will arise “in a place” in the United Kingdom. That being the case, the proposed
developments are action taken to “reduce, control, or mitigate” the effects of the
existing emergency, or are “other action taken in connection with” that emergency (Q).
70. The Claimants submit that the Secretary of State is impermissibly using Class Q as a
policy lever. It is said that there is no connection between section 95 and 98 of the
Immigration and Asylum Act and Class Q. There is a presumption that the Secretary of
State will comply with her statutory duties unless that presumption is specifically
displaced which it has not been. Attention was drawn to the expert report of Dr Darling
which explains that the current crisis has various causes including that Home Office
decision making has slowed down. Having decided it is expensive to accommodate
asylum seekers in hotels, Class Q is being used as a policy lever.
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
71. In my judgment, these submissions to do not assist the Claimants. On the interpretation
of Class Q reached above, the Secretary of State is entitled to rely on Class Q, once
there is a threat of serious damage to human welfare by virtue of homelessness. Its
application does not require an investigation into the causes of the emergency (unless
the reasons for relying on Class Q reach levels of irrationality which entitles a court to
intervene).
Environmental Impact Assessment
Legal principles
72. The relevant legal principles were not in dispute. The following are of particular
relevance to the present case:
a) A screening direction is designed to identify those cases in which the development (i.e.
the project which EU Directive 2011/92/EU requires to be assessed) is likely to have
significant effects on the environment. That assessment is necessarily based on less
than complete information. It is not intended to involve a detailed assessment of factors
relevant to the grant of planning permission, nor a full assessment of any identifiable
environmental effects. There has to be a sensible limit to what a screening decision
maker is expected to do (R (Ashchurch RPC) v Tewkesbury BC (CA) [2023] P.T.S.R.
1377 at §77 and Kenyon v Secretary of State for Housing Communities and Local
Government [2021] Env LR 8 at §15).
b) The question of what may be said to be the project that requires screening, whether
there is sufficient information to issue a screening direction, and whether a proposed
development is likely to have significant effects on the environment, are fact specific
questions of judgement for the primary decision maker, subject to challenge on grounds
of Wednesbury rationality or other public law error (Ashchurch at §81 and Kenyon at
§10 and §12).
c) Relevant factors which may assist in determining the scope of a project include the
following (R (Wingfield) v Canterbury City Council [2020] JPL 154 at §64):
Common ownership: Where two sites are owned or promoted by the same
person, this may indicate that they constitute a single project.
Simultaneous determinations: Where two applications are considered and
determined by the same committee on the same day and subject to reports which
cross refer to one another, this may indicate that they constitute a single project.
Functional interdependence: Where one part of a development could not
function without another, this may indicate that they constitute a single project.
Stand-alone projects: Where a development is justified on its own merits and
would be pursued independently of another development, this may indicate that
it constitutes a single individual project that is not an integral part of a more
substantial scheme.
d) The identity of the project is not necessarily circumscribed by the ambit of the specific
application for planning permission which is under consideration (Ashchurch at §78).
e) The objectives of the Directive and the Regulations cannot be circumvented
(deliberately or otherwise) by dividing what is in reality a single project into separate
parts and treating each of them as a “project”—a process referred to in shorthand as
“salami-slicing” (Ashchurch at §78).
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
f) Other cases, decided on different facts, are only relevant to the limited extent that they
indicate the type of factors which might assist in determining whether or not the
proposed development is an integral part of a wider project (Ashchurch at §80).
g) The existence and nature of cumulative environmental effects will be a question of fact
and judgment in each case (Brown v Carlisle City Council [2011] Env L.R. 5 §21;
Bowen-West v Secretary of State [2012] Env. L.R. 22 at §28; R (Finch) v Surrey County
Council [2022] P.T.S.R. 958 at §15(5)).
h) A decision-maker may rationally reach the conclusion that the consideration of
cumulative impacts from a subsequent development which is inchoate may be deferred
to a later consent stage (analysis of Holgate J in R (Pearce) v Secretary of State [2022]
Env LR 4 at §117 citing R (Littlewood) v Bassetlaw DC [2009] Env. L.R. 21 at pp. 413-
415, particularly §32 and R (Substation Action Ltd v Secretary of State [2023] P.T.S.R.
975 at §198).
Assessing the evidence
73. There can be no doubt that the Planning Response Unit in the Department for Levelling
Up, Housing and Communities proceeded on the basis the development it was required
to screen on each site was a 12 month project. The conclusion reached was that there
would be no likely significant environmental effects from the use of the site as
proposed. Thus, the analysis accompanying the Screening Direction for Wethersfield
states that “The Project is for a 12 month period”. References to the 12 month duration
of the project appear at a number of points in the screening analysis. An example is
“Any resulting social changes would therefore be limited due to the potential
geographical spread and limited numbers passing through the project site over the
temporary 12 month period”. There was no material dispute between the parties in this
regard.
74. Similarly, the environmental consultants instructed on behalf of the Home Office
proceeded on the basis that the development was a 12 month, temporary, project. The
letter dated 17
th
March 2023 from AECOM Ltd to the Planning Response Unit in
relation to Wethersfield states that “The Proposed Development is expected to be
operational for a temporary period of 12 months in total”.
75. The Claimants submit that the Screening Direction failed to assess the likely significant
effects of the project because the evidence shows that the development is likely to last
for longer than 12 months and, as a consequence, its likely significant effects will
endure beyond 12 months. In particular, the Claimants contrast the references in the
Screening Requests and Screening Directions (to the temporary nature (12 month) of
the projects) with internal Home Office decision making documents disclosed in these
proceedings. These documents were not disclosed to the Department for Levelling Up
(responsible for the screening directions). The Claimants point to the stated intention in
ministerial submissions to obtain planning permission on a longer term basis (via a
Special Development Order). They also pointed to a procurement timeline from
December 2022 indicating Home Office plans to contract for the provision of asylum
services with a contract end date of 13 July 2025. As to the latter, it was said on behalf
of the Secretary of State, that the timeline was not specific to the two sites. The
Claimants drew the Court’s attention to emails between officials about external
communications to emphasise what was said to be a ‘disconnect’ between the 12 month
project which was screened and the public and private facing aspects of the project. In
particular:
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
“……In our external communication we remain silent on the
duration and suggest we remain silent with MP and partner
engagement as we continue to review our AO position and
therefore the length of time we occupy the site.
In response to handling duration questions I recommend that we
indicate the temporary nature of use i.e. ‘The Home Office will
use RAF Scampton on a temporary basis.’ Or ‘The Home Office
will only use the site for a limited period of time.’”
(email of 27 March from the civil servant leading the project)
76. The Court was referred to contracts for the provision of services on sites for longer than
12 months (typically 2 years or longer) which were not disclosed in these proceedings
but were obtained by Mr Clarke-Holland’s legal representatives following requests
made under the freedom of information legislation.
77. I start by considering the contemporaneous decision making material generated
between January to March 2023 up to, and including, the announcement in Parliament
on 29 March 2023 about the use of the sites to accommodate asylum seekers.
78. The following extract from the Ministerial submission of 3 March 2023, repeated in
later submissions, is apt to describe the development and the rationale for it:
“To progress rapid development of the Pathfinders and comply
with planning law, we intend to use permitted development
rights for Crown emergency situations (Class Q). Class Q…will
grant us 12 months permission for non-detained use and related
physical works. During this period, we will seek to ensure that
planning permission on a longer-term basis under a Special
Development Order is obtained.”
79. It is apparent from the extract above that Class Q is viewed as a specific and discrete
solution to the need for accommodation. It is said to enable “rapid development of the
Pathfinders” and “will grant us 12 months permission for use and related physical
works.” There was a strong imperative for the 12 month period of permission for the
reasons explained in the Emergency Statement. The statement identifies the statutory
duty on the Secretary of State to accommodate asylum seekers and explains the record
levels in the number of asylum seekers requiring accommodation. The statement goes
on to make the point that obtaining planning permission for new accommodation takes
time”, and “as a consequence, the Home Office is unable to meet the immediate need
for sufficient, adequate accommodation for asylum seekers”. Physical indications of
the temporary nature of the project are the pre-fabricated modular buildings to be
brought onto site and placed on the existing hardstanding, as well as the proposals for
decommissioning by removal of the facilities.
80. It is apparent that the longer term use of the sites, beyond 12 months, was envisaged.
The ministerial submission referred to above states that “we will seek to ensure that
planning permission on a longer-term basis under a Special Development Order is
obtained.” Discussions amongst officials within the Home Office in and around March
2023 were canvassing various different time periods for the use of the sites, often in
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
general terms and by refence to value for money. There was a particular focus on when
to offer West Lindsey District Council an option to purchase the Scampton site.
However, no decision or settled position on the longer term duration of the sites had
been arrived at by the time the Screening Directions were issued. The Equalities Impact
Assessments were based on the assumption that the sites will be used for as long as
expedient, without specifying a precise time period for either site. As is apparent from
the chronology, the decision making was taking place at speed. There are repeated
references in the ministerial submissions to the timing being “Immediate” or decisions
being “urgently required.” The decision making was focussed, primarily, on the use of
the Class Q permitted development right because it offered a quick solution. Counsel
for the Secretary of State summarised the position by explaining that the Secretary of
State was aware that it might be necessary to decommission the sites at the end of the
12 month period if planning permission had not been obtained but that was a risk she
was willing to take for the benefit of the 12 month breathing space offered by Class Q.
81. Aside from the discussions around possible duration of the use of the sites, there is no
contemporaneous evidence before the Court of discussions about the type of any future
development or of the land it would occupy. It is, moreover, apparent that there was
considerable uncertainty about the future, both as to the shape of the development as
well as its duration. The uncertainty stemmed from other efforts underway to reduce
the numbers of asylum seekers requiring accommodation:
“12. …HOAI analysis suggests that the use of the site for longer
than 2 years increases the potential value for money due to longer
return on the initial investment but reduces the certainty as the
long-term position on use of hotels is subject to a number of
factors including the impact of other proposals to reduce demand
for accommodation. Flexibility therefore becomes important
with a longer-term proposal.”
(extract from emails between officials dated 22/23 March 2023)
“Value for Money short-term, this proposal may provide value-
for-money under certain conditions, reliant upon the
counterfactual being the use of more costly accommodation.
Longer term forecasts of supply and demand for asylum
accommodation are changeable and could alter the VFM
assessment of this proposal.”
“ …our recommendation (with HS) is to use the site for 3 years
rather than 2. VfM for 2 years is currently -£2m, i.e. not VfM
(marginal). 3 years is VfM. There are significant variables here
...”
(email of 24
th
March 2023 amongst officials)
“Further that the HS and Minister Immigration’s positions
regards during of use of Scampton is to consider the site for 2
years. The figures continue to move and latest cost estimates for
the site suggest that the current VfM for 2 years is currently -
£2m i.e. not VfM (marginal), which is an update on the position
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
in the submission where it states 2 yrs is VfM. Our latest analysis
indicates that 3 years is VfM and is therefore the safest
assessment at present however this could change as we could
learn more about the site. The Programme will continue to
provide AO advice as costs iterate.”
(email of 27
th
March from the senior civil servant and project
leader)
(underlining in the extracts above is the Court’s emphasis).
82. Further explanation as to the efforts underway to reduce demand for accommodation is
given in the statement by the Minister for Immigration to the House of Commons on
29 March 2023, announcing the use of the sites. The Minister begins his statement by
setting out various measures that are being introduced to tackle illegal migration. The
measures included increased enforcement and removals of people with no right to
remain; Anglo-French co-operation and a partnership with Rwanda to process claims.
The Minister explains that the Home Office was on track to process the backlog of
initial asylum decisions by the end of the year as well as the expected impact of the
Illegal Migration Bill, once adopted. The statement continues “The enduring solution
to stop the boats is to take the actions outlined in our [Illegal Migration] Bill but in the
meantime, it is right that we act to correct the injustice of the current situation.”
83. The Defendants relied on a witness statement, dated 30 August 2023, by Mr Burns, a
project director for the Home Office’s asylum accommodation project. The statement
was accompanied by a statement of truth. Mr Burns explains that there was a general
understanding in the Home Department that the sites were likely to be used beyond the
12 months permitted by Class Q. However, there was no settled intention as to the
duration of any use beyond 12 months or what a “longer-term basis” meant in practice
as this was dependent on a range of factors. Those factors included how the sites operate
in practice; the projected demand for asylum seeker accommodation which in turn was
likely to be affected by a range of other factors, including an increase in the number of
caseworkers to handle asylum claims, improvements in technology and the Illegal
Migration Act 2023, (which received Royal Assent on 20 July 2023). The variable
nature of those factors meant that, while the potential to use the sites for longer than 12
months was a consideration at the time of the decisions in March 2023, whether there
would actually be any longer use, the term of that use and the form of that use were all
necessarily inchoate. At the date of making this statement, no decision to use the sites
beyond 12 months had been taken by the Secretary of State.
84. A witness statement from Mr Banner, another project director, dated 4 April 2023,
explained that “the numbers of future asylum seekers are difficult to predict and the
impact of the Home Office’s other strategies to address the current emergency will
become clearer in the next 12 months. The use of the site under Class Q is not dependent
on the outcome of that process as there is an urgent need for additional accommodation
now.”
85. In addition, evidence from Mr Salmon from the Planning Response Unit, who
conducted the Screening Decision, explains the use of prefabricated modular units,
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
temporary fencing and generators meant he thought it was unlikely that the
development on the project site would be continued beyond the 12 months in the same
form. He judged it likely that the Secretary of State would either stop at that point or
would have decided by then to make a more significant use of the land. He had been
given no clarity about what that more significant use/development would be in terms
of its location, nature, type, and scale. Accordingly, he had no material on which he
could base any assessment of the likely significant effects of future plans.
86. It is well established that a Court will always be cautious in exercising its discretion to
admit evidence that has come into existence after the decision under review was made
as a means of elucidating, correcting or adding to the contemporaneous reasons for it
(R (United Trade Action Group Ltd) v Transport for London & Anor [2022] 1 WLR
367 at §125 (Bean LJ)). The court must avoid being influenced by evidence that has
emerged after the decision. The need for caution is plain. A claim for judicial review
must focus on the reasons given at the time of the decision. Subsequent second attempts
at the reasoning are inherently likely to be viewed as self-serving. Sometimes
elucidatory evidence will be appropriate and necessary, sometimes not. But even where
the evidence in question is merely explanatory, the court will have to ask itself whether
it would be legitimate to admit the explanation given. The Court of Appeal observed
that judges will usually be able to distinguish between genuine elucidation of a decision
and impermissible justification or contradiction after the event.
87. In the circumstances of the present case, I exercise my discretion to permit the
introduction of the evidence of the witnesses for the following reasons. The evidence
of Mr Burns that the use of the sites beyond 12 months was ‘likely’ was relied upon by
the Claimants in their challenge to the nature of the project. All three witnesses are
responding to a challenge about what was not, but should have been, assessed, from
which it follows that the contemporaneous documentation does not address specifically
the points raised by the challenge. However, the explanations provided by Mr Burns
and Mr Banner as to why the future was uncertain is foreshadowed in the
contemporaneous material (set out above). Those references are, however, in shorthand
as the documents are internal and directed to a knowledgeable audience. The witness
evidence assists the Court in understanding the contemporaneous references.
88. The Claimants placed heavy reliance on evidence post dating the screening direction.
This included the award of contracts for the provision of services on the sites. The
earliest contract relied on is one between NHS Mid and South Essex ICB and
Commisceo Primary Care Solutions for the provision of healthcare at Wethersfield for
a period of 18 months which was signed on 21 June 2023. A contract with Clearsprings
Ready Homes Ltd to provide services at Wethersfield for 24 months with a further 12
month extension was signed on 11 July 2023. A 2 year contract was signed with
Portakabin on 11 October 2023.
89. West Lindsey District Council made an application to amend its Statement of Facts and
Grounds to include events post dating the grant of permission for judicial review. The
Council sought to rely, in particular, on the findings of a site visit carried out on 14
September 2023 which were said to indicate that the works being carried out at RAF
Scampton go considerably beyond those in respect of which the EIA Screening
Direction was issued.
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
90. Particular reliance was placed at the start of the hearing on letters dated 27 and 30
October 2023 from the Minister for Immigration to the constituency MPs for the two
sites (Priti Patel MP and Edward Leigh MP) the effect of which, it was submitted,
renders the development retrospectively unlawful. The letters state in material part:
We have always been clear that we would stand up the site in
this initial period using emergency Class Q Permitted
Development Rights while we consider both longer term needs
and the potential to secure ongoing planning permission.
I am therefore writing to inform you that we intend to seek this
further permission via a Special Development Order (SDO) for
a duration of three years.”
91. In the particular context of a challenge to an EIA screening direction, the Court of
Appeal has addressed reliance by parties on documents which were not available to the
decision-maker as follows:
“28 In judicial review proceedings it is generally inappropriate
for parties to seek to rely on documents (and to advance
arguments based on those documents) which were not available
to the decision-maker. Taken at its highest, such an approach
undermines the entire process of judicial review. It runs the risk
that the court will be asked to conduct a kind of rolling review,
in which nothing is ever finalised or settled, and it does not
matter what information was available at the time the decision
was taken. This serves only to encourage the all-too-prevalent
attitude that, in judicial review applications, it is always possible
to “have another go”.
….
30 For these reasons, therefore, I have not had any regard to the
documents that were not in existence or available at the time of
the screening direction.” (Kenyon v SSCLG [2021] Env LR 8 at
§27 30)
92. I accept the Claimants’ submission that evidence post dating a decision may be capable
of throwing light on the contemporaneous decision making. However, in the
circumstances of the present case, evidence post dating the screening direction is, in my
view, an unreliable guide. This is because it is apparent that the decision making was
urgent, conducted at speed and focussed on using Class Q. The future use of the sites
would depend on the outcome of efforts to reduce the demand for asylum seekers and
was to be grappled with once the sites were up and running under the Class Q right.
Accordingly, I discount the evidence relied on by the Claimants that post dates the
screening direction.
93. Accordingly, at the time of the Screening Directions, use of the sites beyond the 12
month period was envisaged. However, no settled plans for the duration or type of use
beyond the 12 month period had been formulated because the future depended, in
material part, on the outcome of efforts to reduce the numbers of asylum seekers
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
requiring accommodation. Future plans for the sites were, as at March 2023, inchoate.
Moreover, it was envisaged that the future plans would be subject to a separate planning
consent process. The references relied on by the Claimants in the emails of officials to
‘handling’ questions about the duration of the use of the sites reflected the, then,
uncertainty as to the future.
Application of legal principles to the evidence
94. Turning then to apply the legal principles to the assessment of the evidence.
95. Both the environmental consultants instructed on behalf of the Home Office and the
Planning Response Unit at the Department for Levelling Up, Housing and Communities
proceeded on the basis the proposed development was a temporary 12 month project.
The decision on the project, including its length, is a matter of judgement for the
decision maker, subject to judicial review on the usual public law grounds (Ashchurch).
96. The formal planning document may not necessarily circumscribe the project
(Ashchurch). However, on the facts of the present case, the Class Q route was seen as
a ‘stand-alone’ or discrete solution to the urgent difficulties faced by the Home Office
in light of the Secretary of State’s statutory duty to accommodate asylum seekers. It
was being pursued by the Home Office independent of any prospect of it continuing
beyond 12 months, albeit it was considered likely that longer use of the sites would be
required. The Secretary of State was aware that it might be necessary to decommission
the sites at the end of the 12 month period if planning permission had not been obtained
by then but this was a risk she was willing to take for the benefits afforded by the 12
month permission. Where a development is justified on its own merits and would be
pursued independently of another development, this may indicate that it constitutes a
single individual project that is not an integral part of a more substantial scheme (R
(Wingfield) v Canterbury County Council at §64).
97. The EIA Directive and the jurisprudence of the European Court of Justice recognise
that it is legitimate for different development proposals to be brought forward at
different times, even though they may have a degree of interaction, if they are different
“projects” (R (Larkfleet) v South Kesteven DC [2016] Env LR 4 at §37). The threshold
for irrationality in the making of such a judgement is a difficult obstacle to surmount
(see e.g. Newsmith Stainless Ltd v Secretary of State for the Environment, Transport
and the Regions [2017] P.T.S.R. 1126).
98. I accept the submission on behalf of the Claimants that the duration of use of the site is
relevant for EIA screening and there is evidence to indicate that the use was likely to
continue beyond 12 months. It is one of the criteria for screening set down in Schedule
3 of the EIA Regulations. However, it is also apparent from the evidence that no
decision about the duration of use of the sites had been made by late March 2023.
Moreover, Schedule 3 of the Regulations refers not only to the duration of the
development but to other factors relevant to screening about which there is no
discussion in the contemporaneous Home Office decision making material. These other
factors include the size and design of any future development; the intensity and
complexity of the development; the magnitude and spatial extent of the impact. The
precise location, nature, type, and scale of any potential future use had not been
discussed. It could involve a different type of development (e.g. involving the
construction of permanent buildings, rather than temporary) and/or a different nature of
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
accommodation (e.g. including some detained accommodation or different types of
non-detained accommodation sites, e.g. a main site and a feeder site). Future plans
might take up more or different land at the sites.
99. The Claimants sought to rely on the decision in R v Rochdale Metropolitan Borough
Council (2001) 81 P&CR 27 §389 and the analysis that where the detail of the future is
uncertain then it is permissible for a screening to proceed on the basis of assessing the
environmental impact understood at the time providing the development is tied into this
envelope, as in the case of Rochdale, by a condition. It was said, by contrast, that the
development permitted under Class Q is in all practical respects an unconditioned one.
I do not accept the submission. Development under Class Q is subject to the paragraph
Q(1)(b) condition that it ceases and is reversed within 12 months. The development
would only continue to operate beyond 12 months if there is further EIA screening and
planning permission granted for the operation beyond 12 months. This is relevant to the
assessment of whether the procedure being followed would have the effect of avoiding
the requirements for the legislation, as in a salami slicing case (R (Together against
Sizewell C) v SS [2023] Env LR 29 at §84).
100. The Claimants sought to characterise the project in the present case as similar to the
bridge, colloquially referred to as the ‘bridge to nowhere' in Ashchurch (§82),
describing the reliance on Class Q as a bridge to the next stage of the project.
However, the context in Ashchurch is distinguishable. In Ashchurch the bridge was
only ever going to be constructed in order to serve the wider development in the
Masterplan area. It had no purpose of its own. As Andrews LJ said in that case, it was
difficult to see how the bridge could not be treated as an integral part of the wider
project, which was a real proposal 100). In the present case the use of the site for 12
months provides the Secretary of State with some (temporary) relief from the acute
accommodation difficulties presented by the numbers of asylum seekers for whom
accommodation must be found.
101. Accordingly, the judgement by the Home Office and the Department for Levelling Up,
that, as at March 2023, for the purposes of the environmental screening, the project was
a 12 month project, cannot be said to be Wednesbury irrational.
102. For similar evidential reasons, I conclude that at the time of the Screening Directions,
there was no obligation to consider the cumulative effects of the proposed development
with any other (or future) use of land at the sites for asylum accommodation. The future
of the sites was too inchoate. Beyond an understanding that it was likely that the sites
would continue in use (if further planning permission was obtained) the discussions
about the future were at such an early stage that there was no reliable information
available to officials to undertake a satisfactory cumulative assessment of any potential
Home Office development beyond the proposed development (R (Littlewood) v
Bassetlaw DC [2009] Env. L.R. 21 at pp. 413-415 and R (Substation Action Ltd v
Secretary of State [2023] P.T.S.R. 975 at §198).
Public Sector Equality Duty
103. Two criticisms were advanced of the Equality Impact Assessments by Braintree and
West Lindsey District Councils. Firstly, it was said that despite recognising the
significant risk of community tensions, the Secretary of State undertook very limited
engagement and consultation with the local authorities and local providers like the
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
police, fire or health services. Instead, she took the ‘in principle’ decision to use the
sites first and proposed to carry out engagement and consultation afterwards. If the
relevant material is not available to fulfil the duty before and at the time when the
decision is being considered, there will be a duty to acquire it, and this will frequently
mean that some further consultation with appropriate groups is required (R (Bridges) v
Chief Constable of South Wales Police at §175).
104. Secondly, by analogy with the decision in R (Hough) v Secretary of State for the Home
Department [2022] EWHC 1635 (Admin) the assessment was not based on a prolonged
period of use of the site and was in the circumstances generalised without site specific
assessment of impacts on local services and the local road network.
105. I am not persuaded by these submissions.
106. What is required of the Court when a breach of the public sector equality duty is claimed
is a realistic and proportionate approach to evidence of compliance with the duty, not
micro-management or a detailed forensic analysis by the Court. The duty, despite its
importance, is concerned with process, not outcome, and the court should only interfere
in circumstances where the approach adopted by the relevant public authority is
unreasonable or perverse. (R (SG) v SSHD [2016] EWHC 2639 (Admin) §329).
107. It is apparent from the disclosed decision making documents that Ministers had taken a
deliberate decision not to undertake formal engagement with local communities about
plans for the sites prior to the announcement in Parliament in late March 2023, save for
limited communication with the local authorities concerned. However, the Home
Office had previous experience with the accommodation of asylum seekers on other
sites. Its experience meant the department was aware, before it took the final decision
to use Wethersfield and Scampton of the potential for community tensions and anti
social behaviour and the need for plans to manage both. The Ministerial submission of
3 March 2023 includes the following analysis:
“38. ……We know from our experience at Linton-on-Ouse that
the lack of any community / local authority engagement ahead
of an announcement negatively impacted public perception of
the project.
……
40. As part of the engagement on previous sites for asylum
accommodation we have engaged key local partners and
stakeholders including the local MP, leaders and Chief
Executives of the county and district councils and blue light
services. Key themes from this engagement which we expect to
be replicated at the Pathfinder sites include:
….
b. anti-social behaviour and Home Office plans to manage this
including keeping local people safe through an increased police
presence in the village;
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
c. the scale of the site and the impact on local community and
services;
d. remoteness of site how will voluntary and legal services
support the site; …”
108. The Department also had experience of dealing with events at Manston in October and
November 2022.
109. Ministers understood that the sites are situated in areas that have not previously been
used to house significant numbers of asylum seekers. Internally, it was acknowledged
that the risk of community tension was significant:
Public sector equality duty and vulnerable individuals
53. As outlined above there is a significant risk of community
tensions which may impact on the Home Office’s consideration
of limb 3: foster good relations…..”
(underlining is the Court’s emphasis)
110. In turn, the equalities impact assessment recognised the importance of minimising the
impacts on local resources. Provision was made for onsite facilities for asylum seekers,
including food, leisure, faith and health facilities so as to reduce the need to rely on
local resources. The need to carefully manage community relations in partnership with
the police, local authorities was acknowledged. It was said that the Home Office will
work with the relevant providers once the site is announced, including establishing a
multi-agency forum bringing together statutory and other agencies on a regular basis.
The assessment describes itself as a living document and references are made to further
review as proposals develop. Specific reference is made for each site to the nearby
primary school which it is said will be discussed as part of the local community
engagement.
111. It was not irrational for the Secretary of State to rely on her department’s understanding
of the likely community tensions from previous experience gained from housing asylum
seekers in other parts of the country. The Claimants have not identified any particular
characteristics of the sites under scrutiny that set them apart from sites in other areas of
the country. The duty of consultation said to be inherent in the duty is the conventional
Tameside duty of inquiry. The obligation on the decision-maker is only to take such
steps to inform himself as are reasonable. Secondly, subject to a Wednesbury challenge,
it is for the public body and not the court to decide upon the manner and intensity of
inquiry to be undertaken. The court should not intervene merely because it considers
that further inquiries would have been sensible or desirable. It should intervene only if
no reasonable authority could have been satisfied on the basis of the inquiries made that
it possessed the information necessary for its decision. (R (Sheakh) v London Borough
of Lambeth [2022] P.T.S.R. 1315 at §73; R (Campaign Against Arms Trade) v
Secretary of State for International Trade [2019] 1 W.L.R. 5765 at §59).
112. There is nothing in section 149 of the 2010 Act which prevents, in an appropriate case,
performance of the duty by means of a conscious decision to undertake equality
assessment on a “rolling” basis. A decision to do that is not, as a matter of law, contrary
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
to the pre-requisites of performance identified in McCombe LJ’s judgment in Bracking
at §26, albeit that a decision maker who decides to proceed on a rolling basis, does so
at their peril (R (Sheakh) v London Borough of Lambeth [2021] EWHC 1745 (Admin)
at §164) (confirmed on appeal). Ministers acknowledged the significant risk of
community tensions, based on its previous experience of housing asylum seekers on
other sites. The parameters of a response to manage the risk were outlined but the
detailed practicalities were left to be determined after the public announcement. The
impact assessment made provision for a further review in this regard. In my judgment,
the Secretary of State had not deferred discharge of her duty, only the detail of the
implementation, which her department had previous experience of managing.
113. In addition, the present case is distinguishable from the case of Hough. Hough
concerned a special development order for 5 years and an equalities assessment which
proceeded on the basis of use of the site for two months. The Court in Hough concluded
that there was a significant difference between a development proposed to continue for
two months and one for five years particularly in respect of the development of
community relations. Pressure on community services would be much greater over a
prolonged period than for only two months.
114. In the present case the Equality Impact Assessments proceeded on the basis that the
length of accommodation on site was for as long as is expedient. On behalf of Braintree
it was said that the assessment should have proceeded on the basis of prolonged use but
for the reasons explained above (in the ground on environmental impact assessment)
the evidence demonstrates that there was no certainty about the duration of the use of
the sites after the 12 month period afforded by the Class Q permitted development right.
Value for Money
115. Braintree District Council sought permission to introduce the ground after permission
had been granted by the Court. The Secretary of State did not object to its introduction
but submitted the ground had no merit.
116. The ground was only dealt with briefly in oral submissions on behalf of by the Council.
In essence, it was submitted that the costs of accommodating asylum seekers in hotels
was a key motivating aspect of the decision making under challenge. The value for
money of the proposed use of the sites was referred to repeatedly in Ministerial
submissions as one of four Accounting Office tests. The Home Secretary was informed
of the need to satisfy the tests and that advice was under preparation by the Accounting
Officer. The advice was finalised on 24 March 2023 and concluded that use of the site
at Wethersfield was cheaper than hotels on the assumption that hotel use will persist in
the short and medium term up to a 5 year period that Wethersfield was expected to be
used for. There was said to be a risk to value for money if hotel use runs for significantly
less than the 5 year period. The advice on this aspect concludes that the Accounting
Officer will need to accept that there is a risk the site could not meet value for money
test. The advice was not shown to the Secretary of State. Instead in the final submission
before decisions were taken, the Secretary of State was told that the Second Permanent
Secretary was content with the value for money analysis. In failing to acquire the
(readily available) information herself, the Secretary of State either failed in the
Tameside duty to acquire information that was necessary to making a lawful decision
or alternatively left out of account a mandatory factor, which was bound to have
relevance to the decisions. It was an obvious enquiry for the Secretary of State to make
Judgment Approved by the court for handing down.
CLARKE-HOLLAND, WLDC & BDC V SSHD & Anr
and the material was readily available within the Home Department and known to
senior officials. In the further alternative, the Secretary of State proceeded on a
mistaken basis, sufficient to amount to an error of law, that the Accounting Officer tests
were satisfied without a specific operational period being identified.
117. I am not persuaded by the submissions, as briefly advanced.
118. The fact that a Minister did not know about, or have their attention drawn to, a relevant
consideration is insufficient by itself to vitiate the decision. A claimant needs to go
further and demonstrate that the consideration was so “obviously material” that a failure
to take it into account would be irrational (R (National Association of Health Stores) v
Secretary of State for Health [2005] EWCA Civ 154 at §6263 and §7375).
119. As Counsel for Braintree Council accepted, the Secretary of State was informed about
value for money considerations in relation to RAF Scampton, because there was a
debate about an option to purchase to be offered to the local authority. Officials
repeatedly informed ministers that the site would need to be used for 3 years to provide
value for money but Ministers indicated their preference for offering the option to the
local authority at 2 years. It is apparent from this debate that the Secretary of State was
prepared to take decisions which she understood did not amount to value for money.
Whilst there is no specific debate about value for money in relation to Wethersfield, the
decision-making context was the same. Given the context of the decision making
(explored in detail in the ground on environmental impact assessment), value for money
was not so obviously material that it was irrational for the Secretary of State to rely on
the submission that her permanent secretary was content with the value for money
analysis without inquiring into the details of the underlying analysis. Other obvious
motivating factors for the decision making included the Secretary of State’s statutory
responsibility to accommodate asylum seekers and the difficulties with current
arrangements with hotels, which extended beyond cost to legal action by local
authorities to prevent the use of hotels. Moreover, Accounting Officers are personally
responsible to Parliament for the stewardship of its resources, not to the Secretary of
State. Nor am I persuaded that the Secretary of State was operating under a mistaken
understanding that value for money was satisfied however long the sites were used for.
There is nothing in the decision making material to indicate an error of this sort.
Conclusion
120. For the reasons given above, the claims for judicial review are dismissed.