Network licence Condition 17 (land disposal): Coal Road, Auchinleck, East
Ayrshire
Decision
1. On 23 June 2020, Network Rail gave notice of its intention to dispose of land at
Coal Road, Auchinleck, East Ayrshire (“the land”), in accordance with Condition 17
of its network licence. The land is described in more detail in the notice (copy
attached).
2. We have considered the information supplied by Network Rail including the
responses received from third parties consulted. For the purposes of Condition 17 of
Network Rail’s network licence, ORR consents to the disposal of the land in
accordance with the particulars set out in its notice.
Reasons for decision
3. We are satisfied that Network Rail has consulted relevant stakeholders with
current information and no objections were received.
4. In considering the proposed disposal, we note that:
there is no evidence that railway operations would be affected adversely;
Network Rail completed the process to remove the land from the strategic
freight site list in 2018; and
no other reasonably foreseeable railway use for the land was identified.
5. Based on all the evidence we have received and taking into account all the
material facts and views relevant to our consideration under Condition 17, we are
satisfied that there are no issues for us to address.
6. We have had regard to our decision criteria in Land disposal by Network Rail:
The regulatory arrangements, October 2019,
1
and balanced our section 4 duties
given to us under the Railways Act 1993. In doing so we have given particular weight
1
Available from https://orr.gov.uk/__data/assets/pdf_file/0007/1996/land-disposal-regulatory-arrangements.pdf.
Les Waters
Senior Manager, Licensing
Email: les.waters@orr.gov.uk
22 July 2020