7
The following reflects the only previous incident reported to the BSEE that occurred at the
Khamsin while under contract with TEPUSA:
On July 29, 2020, a rig crane crew lowered a bundle of stanchion posts from the pipe
deck to the moonpool area to store them for future use. Before the lift began, the bundle
was wrapped and secured with slings, wire rope, and clamps to stabilize the load. During
the lift, the rig crane crew guided the load from the pipe deck to the moonpool area. Once
the bundle landed, a roustabout designated for the job began removing the slings rigged
up to the load. While removing the slings, one of the stanchion posts in the bundle shifted
and landed on the roustabout’s foot. The rig crane crew raised the load to free the
roustabout’s foot. The roustabout was transported to shore for medical evaluation and
diagnosed with a foot contusion.
BACKGROUND OF OPERATIONS
The Rig Floor Crew (RFC), consisting of five floorhands and one assistant driller, involved in
the incident arrived to the Khamsin on August 5, 2020, and August 12, 2020. Upon arrival,
members of the RFC completed the onsite orientation, which covered critical safety topics such
as emergency response, hazards, permits, chain of command, and incident reporting. In the days
that led up to the incident on August 23, 2020, the Khamsin was in the process of drilling South
Platte Well #001 to a True Vertical Depth of 30,181 feet. Once the intended depth of 30,181 feet
was reached, well fluids were circulated out of the work string as the rig commenced pulling the
drill pipe out of the hole in preparation to run and set a liner. After the liner shoe was set at
30,135 feet, rig supervision decided to suspend well operations due to the threat of Tropical
Storms Laura and Marco. To temporarily suspend well operations, a storm packer was installed
at 5,630 feet, where it was successfully pressure tested to 1,800 psi to ensure sufficient integrity
in the well. After the storm packer was confirmed to be stable, the Blind Shear Ram on the
subsea BOP was successfully pressure tested to 1,800 psi. After the riser was displaced with
seawater, the Khamsin was ready to disconnect the LMRP from the lower subsea BOP stack.
Once the disconnect occurred, the Khamsin personnel continued to monitor the Tropical Storms’
trajectory as preparations were being made to pull and lay down riser joints on the rig floor.
INCIDENT HISTORY AND TIMELINE
On August 23, 2020, at 0000 hours, the RFC began arranging their respective work plans
required for the Khamsin to depart the GB Block 1003 location safely. To successfully complete
the riser pull operations, the six members of the RFC were assigned to various tasks. A team of
two floorhands were assigned to the forward side of the riser joint (referred to as the Forward
Team) and a team of two floorhands were assigned to the rear side of the riser joint. On each
team, one floorhand was the Hydraulic Torque Wrench (HTW) Operator, whereas the other
floorhand was the HTW Assistant. The HTW Assistant oversaw the progress and helped the
HTW Operator by using a fork tool to ensure the bolts were retained in the upper flange once
they were nearly backed out. Additionally, one floorhand was designated as the Hydraulic Utility
Winch (HUW) Operator, whose responsibility was to adjust the height of the HTWs by using an
electronic remote that controlled the HUW. Furthermore, the Assistant Driller acted in the role of
Drill Floor Observer (DFO), who monitored the rig floor red zone to identify any unsafe
practices or hazardous equipment in motion.