HB-1-3560
CHAPTER 9: PROJECT CONSTRUCTION
9.1 INTRODUCTION
Management of construction is the borrower’s responsibility. However, the Agency will
monitor construction to ensure that it complies with the project plans and specifications and to
protect the government’s security interest. Consequently, the Agency plays an active oversight
role in the construction process, from reviewing planning documents to inspecting construction
work. This chapter describes the Agency’s procedures for carrying out these responsibilities. It
summarizes the requirements established under RD Instruction 1924-A, and RD Instruction
1924-C.
The chapter is organized as follows:
Section 1 describes construction requirements, including construction standards,
contracting methods, contractor requirements, and cost certification procedures.
Section 2 describes the contracting procedures from the invitation to bid through the
preconstruction conference and the notice to proceed.
Section 3 describes the Agency’s responsibilities during construction, including
inspections, concurrence in change orders and contractor payments, and the contract
close-out process.
9.2 OVERVIEW OF THE AGENCY’S ROLE IN THE CONSTRUCTION PROCESS
The Agency’s involvement in the construction process begins with the submission of the
initial application. The State Architect reviews all construction documents, beginning with the
preliminary planning documents and concluding with the final plans, specifications and cost
estimate. The State Architect will advise the loan approval official on acceptability of the project
design, specifications, and cost estimates before the loan is closed or construction begins
(whichever occurs first). The State Architect will also consult with the State Environmental
Coordinator regarding any mitigation measures required by the environmental review, which
may affect project plans and specifications. The State Architect acts in an advisory role to the
processing and approval officials, unless specifically delegated responsibility for “approval” of
design, contracts, etc.
The Agency concurs in the borrower’s selection of a contractor and in the construction
contract. The Agency requires that a preconstruction conference be held, as described in
Paragraph 9.11.
During construction, the Agency assumes an oversight role, performing inspections and
concurring in change orders and contractor payments. The Agency also performs a final
inspection before contract close-out.
(
Note: The Agency’s role in construction oversight does not diminish the role of the
project architect hired by the borrower. The project architect is responsible to the borrower for
9-1
(02-24-05) SPECIAL PN
HB-1-3560
ensuring that the project is constructed according to the Agency-accepted plans and
specifications. The project architect’s responsibilities include regular inspections, payment
certifications, change order approvals, and other oversight of construction activities.)
9.3 CONSTRUCTION FINANCING
There are two methods of financing construction: interim financing and multiple
advances.
Interim financing. If the borrower obtains interim financing, an interim lender
provides the funds for construction and the Agency does not close its loan until after
construction. The Agency prefers to use interim financing whenever possible since it
is, in essence, financing a finished product.
Multiple advances. If the borrower obtains multiple advances, the Agency advances
funds to the borrower to pay for construction as the work progresses. If multiple
advances are used, the borrower must document that interim financing is not available
at suitable rates or terms.
These methods are described in Chapters 4 and 5. Regardless of the method used, the
Agency will assist in monitoring the construction process as described in this chapter.
9.4 IDENTIFY-OF-INTEREST RELATIONSHIPS
If any parties in the construction process have an identity-of-interest (IOI) relationship
with the borrower, the following steps must be taken:
The borrower must disclose the IOI relationship to the Agency;
The construction costs must compare favorably with projects not involving an IOI;
and
The contractor must certify all actual costs in accordance with cost certification
procedures described in Paragraph 9.8.
9-2
HB-1-3560
SECTION 1: CONSTRUCTION REQUIREMENTS
9.5 CONSTRUCTION STANDARDS
Construction standards are prescribed in RD Instruction 1924-A. Projects must be
designed to meet or exceed:
The development standard adopted by the Agency in the State where the project is
located;
Agency thermal performance standards; and
Applicable state and local laws, ordinances, codes, and regulations.
Land and site development must meet the standards and requirements in RD Instruction
1924-C. These requirements are discussed in Chapter 3. The project architect must certify that
the final plans and specifications comply with these standards prior to Agency approval of the
loan. Form RD 1924-25, Plan Certification, must be used for this purpose. In addition, the
project architect must also certify that the project has been designed in accordance with all
applicable accessibility standards and guidelines. These standards may include, but not be
limited to, the Uniform Federal Accessibility Standards (UFAS), the Fair Housing Act
Accessibility Guidelines (FHA/AG), the Americans with Disabilities Act Accessibility
Guidelines (ADA/AG), and any applicable State or local requirements.
9.6 METHODS OF CONSTRUCTION
There are three methods of constructing Multi-Family Housing projects: competitive bid
contracts, negotiated bid contracts, and owner-builder.
A. Competitive Bid
All construction contracts must be awarded by competitive bid unless an exception is
granted for a negotiated contract or the owner-builder method of construction, as
described in Paragraphs 9.6 B and C.
For competitive bidding, the borrower provides public notice inviting contractors to
submit a bid within a specified time frame. Contracts are selected based on cost and
awarded to the lowest responsible bidder.
The contractor and the contract price must have Agency concurrence. The contractor
must be licensed as required by the State and must not be on the list of debarred
contractors. Unless waived by an interim lender, the contractor must provide a
performance and payment bond or an acceptable alternative as described in RD
Instruction 1924-A.
The competitive bidding process is discussed further in Paragraph 9.9.
9-3
(02-24-05) SPECIAL PN
HB-1-3560
B. Negotiated Contract
Borrowers may request an exception
from competitive bidding if they prefer to
use a specific contractor or if the
competitive bidding process does not yield
an acceptable bid. Negotiated contracts are
often used by borrowers with a
construction company having an IOI. The
State Director may grant an exception only
if the following conditions are met:
Competitive Bids and
Negotiated Contracts
At times of high-construction
activity when construction prices tend to be
higher, negotiated bids may provide lower
costs. At times of low-construction
activity, competitive bidding is more likely
to yield lower costs.
The cost under the negotiated contract compares favorably with similar and recent
construction in the market area;
The proposed contractor is a reliable contractor and licensed to perform the
construction work in accordance with local requirements where the project is located;
and
The reasons for requesting the exception from competitive bidding are documented.
The information required for a written request to grant an exception to the
competitive bidding requirements must be in accordance with RD Instruction 1924-A.
C. Owner-Builder [RD Instruction 1924.13(e)(2)]
The Owner-builder method of construction is used when the construction company is
identical to the borrower/owner entity. Owner-builders must be qualified to perform the
construction work and show that they are licensed in accordance with local requirements
where the project is located. There is NO written agreement or contract between the
borrower and the construction company to build the project. However, there will be
separate contracts with companies to perform portions of the work, such as plumbing and
electrical systems.
Before granting an exception to allow an owner-builder arrangement, the Loan
Originator and the State Architect/Engineer will review the borrower’s written request,
drawings, specifications, and cost estimates to determine whether the arrangement is in
the best interest of all parties. All borrowers with owner-builder construction
arrangements are required to certify the final construction costs as described in Paragraph
9.8.
The information to be included in the borrower’s written request must be in
accordance with RD Instruction 1924-A.
9.7 CONTRACTOR REQUIREMENTS
The Agency must ensure that the contractor meets the requirements described below.
9-4
HB-1-3560
A. Debarment and Suspensions
All contractors submitting a bid in excess of $25,000 must certify that they are not
currently debarred or suspended from participating in Federally funded programs. The
certification statement is included on Form AD 1048, Certification Regarding
Debarment. Failure to submit the certification is grounds to reject the bid. It is the
Agency’s responsibility to check the list of debarred and suspended contractors to make
sure the contractor is not listed there (even if the contractor has submitted the
certification).
B. Insurance
The contractor must have property and liability insurance for construction to protect
the borrower and contractor from a variety of losses. The construction contract must not
become valid until proof of insurance is received by the Agency. The amount of
coverage and the other insurance provisions of the coverage must be in accordance with
the project’s construction documents.
C. Payment and Performance Bonds
Payment and performance bonds covering the contractor’s work must be executed
prior to the start of any construction. The bonds must each have a face value of 100
percent of the construction contract. These surety bonds must only be obtained from a
corporate bonding company listed on the current U.S. Department of Treasury Circular
570 (published annually in the Federal Register), as holding a certificate of authority, as
an acceptable surety on Federal bonds, and as legally doing business in the State where
the project is located.
If interim financing is involved, the interim lender may waive the bonding
requirement. The waiver must be in writing and attached to the contract documents.
An alternative to the bonding requirement is a letter of credit. Requirements for
letters of credit are discussed in Paragraph 9.7 D.
D. Letters Of Credit
In lieu of payment and performance bonds, the lender (or in the case of multiple
advances, the Agency) may accept an unconditional and irrevocable letter of credit issued
by another lending institution to secure the completion of construction. The letter of
credit must equal the amount of the construction contract and must remain in effect until
the date of final acceptance of work by the owner and the lender (or the Agency). In
addition, the letter of credit must stipulate that the lending institution that issued the letter
of credit, upon written notification by the owner or lender (or the Agency) of the
contractor’s failure to perform under the terms of the contract, will provide payment up to
the amount of the contract to satisfy all prior debts incurred by the contractor in
performing the contract and all funds necessary to complete the work.
9-5
(02-24-05) SPECIAL PN
HB-1-3560
An irrevocable Letter of Credit issued by a bank or other approved financial
institution must meet strict credit quality requirements (see Exhibit 9-1 for credit quality
requirements) and be for 100 percent of the construction contract. Further requirements
for letters of credit include:
The issuing institution must not be an affiliate of the lender, unless it has an
acceptable rating from an approved rating agency, which is not an affiliate of the
lender;
Federal Home Loan District Bank-enhancement of a member bank letter of credit is
an acceptable method for meeting Agency credit standards;
Rural Development, USDA, must be named as the sole beneficiary;
The term must be a minimum of 1 year; and
The form of the letter of credit and the sight draft must be reviewed and approved by
the Agency.
Exhibit 9-1
Credit Quality Requirements for Letters of Credit
Rating Agency Type of Collateral Rating
Thomson’s Bankwatch N/A B or better
S&P Long-term senior debt, if rated,
or long-term bank deposit
A or better
Moody’s Long-term senior debt, if rated,
or long-term bank deposit
A or better
E. Warranties
At the time the project is determined ready for occupancy, the contractor must
execute Form RD 1924-19, Builder’s Warranty, providing a 12-month warranty on work
performed and materials supplied.
F. Compliance with Civil Rights Requirements
The applicant/borrower must comply with all applicable civil rights requirements. A
partial list includes:
Architectural Barriers Act (ABA);
Section 504 of the Rehabilitation Act of 1973 and UFAS;
Americans with Disabilities Act and ADA/AG;
9-6
HB-1-3560
Fair Housing Act and FHA/AG;
Executive Order 11246; and
Any State or local requirements.
9.8 COST CERTIFICATION
In certain cases the borrower, contractor, subcontractors, and suppliers must each provide
a certification of the actual costs of construction. Appropriate circumstances for cost
certification include:
All situations where there is an IOI; and
Other cases deemed appropriate by the Agency. For example, the Agency may
request cost certifications to assist in cost tracking and help determine whether bids
on future projects are reasonable.
Cost Certification will be performed in accordance with § 1924.13 (e)(1)(v).
The actual direct costs to the company with an IOI with the borrower must be reported on
Form RD 1924-13, Estimate and Certificate of Actual Cost and audited by a licensed Certified
Public Accountant (CPA) in accordance with Government audit standards (GAS). The audit
may be contracted out by the Agency.
Reviewing construction costs is an ongoing process for Agency staff, beginning with the
preliminary cost estimate provided in the initial application through the final payment to the
contractor.
A short summary of the cost review process is provided in Exhibit 9-2.
9-7
(02-24-05) SPECIAL PN
HB-1-3560
Exhibit 9-2
Overview of the Cost Review Process
The Loan Processing Staff will:
y Compare the applicant’s preliminary cost estimate to historic costs and
nationally recognized cost databases and discuss any concerns with the
applicant.
y Review the applicant’s cost estimate provided on Form RD 1924-13,
and ensure any previous concerns were addressed satisfactorily.
y Review payment requests and change orders to check arithmetic and
verify that totals do not exceed contract limits.
y Review the final payment request and the cost certification provided on
Form RD 1924-13.
9-8
HB-1-3560
SECTION 2: CONTRACTING PROCEDURES
9.9 COMPETITIVE BIDDING PROCEDURES
The borrower is responsible for following proper bidding procedures in accordance with
RD Instruction 1924-A. Generally, the project architect oversees the bid invitation and selection
process. The Agency serves only in an oversight role to ensure that proper bidding procedures
are followed.
The purpose of competitive bidding is to obtain acceptable construction services for the
lowest costs possible. To be successful, the process must maximize open and free competition.
Conditions must not exist or be established that would give preference to a specific bidder or
type of bidder. If no acceptable bids are received, the borrower may competitively rebid the
contract or proceed to a negotiated bid, subject to Agency approval.
A. Contents of the Bidding Package
For competitive bids, the project architect prepares documents to be distributed in the
bidding package. The bidding package must include the items listed in RD Instruction
1924.13(e)(1)(ii).
B. Distribution of the Bidding Packages
The invitation to bid must be distributed to all interested parties. The borrower may
send the invitation directly to specific contractors from whom bids are desired, but public
notice must always be required so that other contractors have an opportunity to bid.
Prospective bidders can be informed of requests for bids through publication in local
newspapers, plans services and similar services.
9.10 AGENCY CONCURRENCE IN THE CONTRACT
Normally, the borrower, project architect, bidders, and interested persons attend a bid
opening. An RD representative should attend each bid opening. The RD representative is an
observer, not a referee, and as such cannot waive bidding requirements and should not address
any questions concerning bid acceptability, responsiveness of bids, responsibility of bidders, etc.
A. Review of the Bid
The borrower must submit the following for Agency review:
A bid summary that shows the project architect’s estimate of costs and all bids
submitted.
A revised final cost breakdown on Form RD 1924-13.
9-9
(02-24-05) SPECIAL PN
HB-1-3560
The project architect’s recommendation. (If the project architect does not recommend
that the bid be awarded to the lowest bidder, the recommendation must include a
justification for an award to a higher bidder, or, to accept no bids.); and
Documentation of the borrower’s decision (copy of the bid selected).
Loan Processing Staff should review the bid documentation to confirm the following
items:
The selected bid is properly completed including the bid bond;
Based on the revised final Form RD 1924-13, there is enough money is to cover the
construction costs; and
The project architect has provided sufficient justification for the borrower’s bid
selection.
After these items have been reviewed, the Agency should advise the borrower in
writing of any problems or of its concurrence with the bid award.
B. Contract Documents
The borrower may use the construction contract form published by the American
Institute of Architects (AIA Document A-101) with the Agency-approved amendment
(RD Instruction 1924-A, Guide 1, Attachment 6). RD Instruction 1924-A also references
use of Agency forms for MFH and other more complex projects. Other contract
documents, acceptable to the Loan Approval Official and containing the requirements of
RD Instruction 1901-E may be used provided they are customarily used in the area and
protect the interest of the borrower and the Government. In such cases, the OGC should
be consulted.
The construction contract must contain the nondiscrimination language required by
Executive Order 11246 and regulations issued by the Department of Labor (DOL). That
language may be found in the DOL regulations at 41 CFR 60 [§ 60-1.4(b)] and on pages
2 through 4 of Form RD 1924-6, Construction Contract.
A contract is signed and concurred in by the State Director (or his/her delegate) after
it is signed by the borrower and contractor. The Agency is not a party to the contract and
does not incur any liability under it, but still must ensure that the borrower and the
contractor comply with all applicable regulatory requirements.
Loan Processing Staff should maintain all construction-related documents in the
borrower’s construction file. A complete list of contract documents is provided in
Exhibit 9-3. See RD Instruction 1924-A for more guidance on contract documents
(1924.13(e)(1)(ii) and Guide 1).
9-10
HB-1-3560
9.11 PRECONSTRUCTION CONFERENCE
Once the contract is awarded and executed, all interested parties must attend a
preconstruction conference. The conference serves to clarify arrangements and expectations in
advance to avoid conflicts later in the construction process. Form RD 1924-16, Record of
Preconstruction Conference, or an industry equivalent may be used as a guide for an agenda.
The preconstruction conference should include the borrower, contractor, architect, lender
representatives (if interim financing was obtained), and an Agency representative. The project
architect should lead this meeting. It should cover, at a minimum, the following items:
Responsibilities of all parties, including the contractor, the Agency, and the borrower,
including identifying the authorized representatives for each entity;
The work to be undertaken;
Applicable wage rates and The United States Equal Employment Opportunity
Commission (EEOC) requirements;
The U.S. Department of Labor Occupational Safety and Health Administration
(OSHA) requirements;
Contractor’s use of the site (parking, security, permits, dust control);
Protection of stored materials;
Mitigation measures required by the environmental review;
Procedures to be used for inspection, change orders, and payment requests;
Timeframes for starting and completing work;
Requests for extending contract times;
The contract agreement and any subcontracts;
Dispute resolution procedures; and
Close-out procedures.
9-11
(02-24-05) SPECIAL PN
HB-1-3560
Exhibit 9-3
Contract Documents
Advertisement for Bidders;
Instructions for Bidders;
Bid;
Bid Bond;
Form RD 400-6, Compliance Statement
Notice of Award;
Form AD 1048, Certification Regarding Debarment and Suspension
RD Instruction 1940-Q, Exhibit A-1, Disclosure of Lobbying Activities
Agreement between Owner and Contractor
Certificate of Owner’s Attorney;
Contract Concurrence;
Payment Bond;
Performance Bond;
Notice to Proceed;
General Conditions of the Construction Contract ;
Form RD 3560-31, Identity of Interest Disclosure/Qualification Certificate;
Drawings and specifications;
Contract Change Order;
Payment request or certification;
Labor Standards Provisions, only for projects subject to Davis-Bacon
Wage determinations (Department of Labor); and
Form RD 1924-19 Builder’s Warranty, or equivalent.
9-12
HB-1-3560
9.12 NOTICE TO PROCEED
The Notice to Proceed establishes the contractor’s permission to proceed with
construction. It gives the contractor permission to go to the borrower’s land and begin work, and
it identifies the start date for the time period of the contract. It is issued by the borrower after the
contract has been executed and the preconstruction conference has concluded. It is signed by the
borrower and the contractor. The Notice to Proceed should not be issued until the Agency loan
is closed (for multiple advances) or the interim lender has concurred (for interim financing).
9-13
(02-24-05) SPECIAL PN
HB-1-3560
This page intentionally left blank
9-14
HB-1-3560
Who Performs Inspections?
Several parties have an interest in the
satisfactory completion of project construction
and, therefore, conduct inspections.
y The project architect has the primary
responsibility for performing regular
inspections. These inspections should take
place at least monthly and serve to
document partial payment requests.
y An Agency representative with sufficient
knowledge of MFH construction should also
inspect the property on a monthly basis and
as needed. It is good practice for the
Agency architect to coordinate with the
project architect to perform joint inspections
and to time these inspections with partial
payment requests.
y The interim lender (if there is one) is also
encouraged to make inspections of the
SECTION 3: CONSTRUCTION OVERSIGHT
9.13 PROGRESS INSPECTIONS
The borrower maintains full responsibility for the quality of construction; however, the
Agency must still take steps to protect the value of its investment. Consequently, the Agency
must conduct periodic progress inspections to ensure that work is proceeding as planned. These
inspections must be performed by persons with knowledge of MFH construction and experience
in conducting Agency inspections.
A. Timing of Inspections
Inspections must take place prior
to authorization of partial payments,
normally at least monthly. In
addition, the following three
inspections must take place for each
building:
The initial inspection must be
made just prior to or during the
placement of concrete footings or
monolithic footings and floor
slabs.
Another inspection must be made
when the building is enclosed;
structural members are still
exposed; roughing in for heating,
plumbing, and electrical work is in
place and visible; and wall
insulation and vapor barriers are
installed. Customarily, this is
prior to installation of brick veneer or any interior finish materials.
The final inspection must be made when all development has been completed and the
project is ready for occupancy for its intended use.
9-15
(02-24-05) SPECIAL PN
HB-1-3560
B. Inspection Procedures
Actual construction work needs to be inspected to determine and verify that terms and
conditions of the construction contract are met. The project plans and specifications
signed by all parties are used to judge the acceptability of the work. Items that do not
meet these or other contract documents must be either removed, corrected, or in some
cases accepted with an adjusted price.
The Agency inspector must use Form RD 1924-12, Inspection Report.
The inspection report must provide a description of the conditions seen, especially
those that differ from the plan and specifications. Discrepancies with the plans and
specifications must be brought to the attention of the project architect and
documented until the issue is resolved.
For inspections prior to making payment, the inspector must confirm the estimated
values of work completed and properly stored materials and itemize the percent of
work complete for each task. Payments must be adjusted if there are any
discrepancies.
If environmental mitigation measures are required and included in the construction
contract, the inspector must document compliance with such measures on the report.
Noncompliance with mitigation measures should be reported promptly to the Loan
Originator.
A (pre-final) inspection must be made to determine if the project is ready for
occupancy. If so, the project architect must issue a Certificate of Substantial
Completion and submit a written report (punch list) of the work yet to be completed
to the owner, the contractor, and the Agency. The project architect should notify the
Agency in sufficient time for the Agency to participate in the inspection. The owner,
project architect, Approval Official, and State Architect should jointly participate in
the inspection. The Agency should receive a copy of all inspections from applicable
regulatory authorities at this time.
The inspection report must be signed by the Agency inspector.
Copies of all inspection reports (by the Agency inspector, the project architect, and
any other inspectors, e.g., local, State, fire marshal) should all be kept in the
construction file by the Agency.
9-16
HB-1-3560
9.14 CHANGE ORDERS
Change orders are used to address changes in: facility design; labor or material or their
cost; or the time requirement of the project. They are used when an owner, the project architect,
or local authorities require changes in the work or other unforeseen circumstances require a
change in the contract’s scope of work. Any changes that occur after a contract is executed and
affect project design, materials, costs, scope, or schedule must be documented as a contract
change order. The owner, with the assistance of the project architect, will obtain Agency
concurrence in writing for all change orders
prior to the performance of the work. The change
order becomes a part of the construction contract. Form RD 1924-7, Contract Change Order, or
its equivalent must be used. Changes that are deemed minor and do not affect costs should be
documented as field orders by the project architect.)
Generally, total changes to the work should not exceed 20 percent of the original
contract cost. If changes exceed this threshold, an increase in performance and
payment bonds will be necessary.
The change order must be supported by a cost breakdown, including any profit and
overhead. No additional profit or overhead is allowed in IOI cases if either totals
more than the amounts included in the final Agency-approved cost estimate on Form
RD 1924-13.
If the change orders result in an increase in project costs, there are several ways to
pay for these costs:
The borrower finds the funds elsewhere.
Costs are reduced from another part of the project, and a deductive change order
is executed to document that change. Where funds are derived from reductions in
other portions of the work it is critical to assure that these changes to not affect
the overall value of the project. It may be necessary to refer such changes to the
appraiser for this determination.
In rare cases, the Agency may make a subsequent loan. Subsequent loans may
only be made to complete, improve, repair, or make modifications to a project.
Subsequent loan funds may not be used to reimburse an owner for additional
contributions that were made to complete a project. In addition, no commitment
for additional funds will be made by the Agency unless, and until, additional
funds have actually been obligated. Finally, if a subsequent loan is made, the
borrower equity and initial operating capital contribution requirements apply, and
the total amount of the combined loans may not exceed 95 percent of the
appraised value, or total development cost, whichever is less.
9-17
(02-24-05) SPECIAL PN
HB-1-3560
No increase in per-unit development cost will be approved, whether the
circumstance causing the cost increase occurs before, during, or after the
construction period, unless these conditions were unforeseen factors beyond the
owner’s control; design changes that were required by the Agency or local
government; or changes in financing that were approved by the Agency. Any
increase in cost must be approved by Rural Development in writing before the
expense is incurred.
Under no circumstances will a cost increase request be approved without
concurrent agreement between Rural Development and the applicant/borrower as
to how the cost increase will be funded. In most cases, this will mean that the
owner will need to contribute additional funds.
If the change orders result in a decrease in project costs:
Unused funds may be used to cover certain other eligible project costs only if they
were unknown to the borrower at the time the loan was approved.
Otherwise, the amount of the loan will be decreased and the funds deobligated.
Change orders do not generally require preparation of Form RD 1940-22,
Environmental Checklist for Categorical Exclusions or amendment of the original
environmental assessment, provided that the action will not alter the purpose,
operation, location, or design of the project as originally approved.
9.15 PARTIAL PAYMENTS
The borrower and the Agency must take proper precautions to ensure that all payments
made to the contractor are properly applied against bills for materials and labor procured under
the contract.
Form RD 1924-18, AIA Form G702, or other professionally recognized form that
contains architect certification and approval, approval of the borrower, and conditional
concurrence of Agency must be used. If the Agency form is not used, Agency concurrence
language must be added to the form used.
The following procedures must be used in approving construction payments:
Payment requests are submitted by the contractor to the owner. The request must
include a statement showing total amount owed to date for material and labor
procured under the contract. It may also include evidence showing that previous
partial payments were applied properly. The payment requests should provide the
same breakdown of construction costs as the final and approved cost estimate before
construction began.
9-18
HB-1-3560
The breakdown of cost items in the payment requests must be the same used in the
final Agency-approved cost estimate on Form RD 1924-13.
The project architect and the borrower must review the request and confirm its
accuracy, based on a site inspection, before signing and forwarding it to the Agency.
Payment requests may include costs associated with a change order only when the
change order is approved by the Agency. Each approved change order should be
entered as a separate cost line item on the request form.
The Agency will concur with the or require revision to the amount of partial payment
based on a site inspection.
The borrower must retain a percentage of the amount due the contractor in
accordance with RD Instruction 1924-A until all work has been completed and
accepted. The surety company that issued the payment and performance bonds, if
applicable, must provide a written consent for the retainage to be released. Retention
percentages must be clearly articulated in the construction contract. When
construction is determined to be substantially complete, but some work remains to be
completed, an amount adequate to cover any remaining work items must be withheld
from the contractor. See Paragraph 9.17 for a discussion of final payments at contract
close-out.
9.16 OBTAINING THE CHECK FOR MULTIPLE ADVANCES
Once the Agency has approved the payment request, the Loan Servicer must order the
check using AMAS. Note that the check request will take approximately
5 days from request to
receipt.
When the check is received it is deposited in the supervised bank account in accordance
with RD Instruction 1902-A. As work is completed, the Agency can release these funds to the
borrower. If all work for that payment request is completed at the time of check receipt, the
entire amount of the check can be released immediately to the borrower.
It is important to monitor the maximum debt limit (MDL) for the loan. The Loan
Servicer should insure that that the disbursed amount plus accrued interest does not exceed the
MDL.
9.17 CONTRACT CLOSE-OUT
When work is complete, the contract is closed out—all payments are made and all claims
are released. However, prior to close-out, the Agency and the borrower must ensure that all
work was performed according to the contract and that it meets acceptable standards.
9-19
(02-24-05) SPECIAL PN
HB-1-3560
A. Final Inspection
The project architect should coordinate the final inspection with all parties, including
the Agency and the interim lender's fee inspector (if applicable), so that all inspectors
may be present on the site at the same time. A final inspection must be conducted before
the final payment to the contractor to ensure that all work is performed according to
project plans and specifications and meets all applicable codes and quality standards. If
the project is receiving interim financing, the Agency loan must not be closed until this
inspection is performed.
A final inspection is conducted when all construction work is completed, including
any punch-list items, and the project is fully ready for its intended use. The owner shall
acknowledge final acceptance by signing an Agency inspection report. The final
inspection will be made at the earliest possible date after completion of the planned
development. When several buildings are involved, inspections may be made upon
completion of each building. No inspection will be recorded as a final inspection until all
deficiencies or nonconforming conditions have been corrected. When codes and
ordinances require inspections by local authorities, their final acceptance will be required
prior to the Agency's final inspection and acceptance.
B. Final Payment
The final payment to the constructor will be based on the results of the final
inspection. Before the final payment can be made, the final documents as listed below
must executed:
Form RD 1924-9, Certificate of Contractor’s Release, or other professionally
recognized form.
Form RD 1924-10, Release by Claimants, or other professionally recognized form.
Form RD 1924-19, Builder’s Warranty or equivalent, and any related documents
required by the contract.
Acceptance by responsible public authority. When local or state codes and ordinance
require inspections, final acceptance by the local authority will be required prior to
final inspection. A certificate of occupancy may be evidence of this inspection.
Final Certificate of Payment by the project architect.
Cost certification, if applicable.
If work cannot be completed due to weather or other extenuating circumstances (e.g.,
landscaping work that cannot be done during the winter), the borrower will withhold
funds to ensure completion of the work. Usually, the amount withheld is 1.5 to 2 times
the dollar value of the work completed. (This serves as an incentive to the contractor to
9-20
HB-1-3560
return and complete the work.)
Interim funds remaining because of early completion of construction will be returned.
The leftover interest may be used for certain other eligible loan purposes critical to the
completion of the project that were unknown to the applicant and contractor at the time
the loan was approved.
9-21
(02-24-05) SPECIAL PN